Bypass path and Bilsdean temporary traffic lights
Branxton Project will be starting the bypass path in the opposite field South of the C120 on the 2nd February with one weeks work planned to complete ahead of road widening works & traffic management starting 16th February. Location shows on the map (path is in blue).
They have planned dates for the traffic lights and material movements through Bilsdean in February as below:
Monday 02- Friday 06 February inclusive
Monday 09- Thursday 12 February inclusive
Monday 16- Thursday 19 February inclusive
Monday 23- Thursday 26 February inclusive
SP Energy Networks have advised that the email address previously provided for queries about the Branxton Substation works has been experiencing issues. From now on, please direct any enquiries to: