UPDATE  on Branxton Substation Road Closures 

from SP Energy Networks



Please be aware that the previously advertised phase one road closure has been extended due to unforeseen circumstances and will now be in place until Friday 25th September.


Once the Phase one closure has been lifted, Phase two will be implemented and will remain in place until Monday 12th October.


We apologise for any inconvenience this may cause.


Thursday 27 August – Friday 25th September (was 13th September).

Phase one – A full road closure will be in place on the C121 between Blackcastle cottage and the junction with the U215. Please note the U215 will remain open throughout. This is detailed, along with the diversion in Image below. This will allow further junction works to be carried out where the haul road crosses the public road.

Friday 25th September (was 13th September) to Monday 12th October

Phase two – a full closure of the section of the C121 between the junction of the U215 and the existing substation will be required to facilitate utility diversion works. This is detailed in image below. The U215 will remain open throughout.



We would like to clarify that those living in properties around the closure site, will be able to access their properties throughout the works.


SPEN are currently working with the Community Traffic and Transport Group to review tree and hedgerow removal on the C121. SPEN have undertaken to review plans and refer back to the community prior to any associated tree and hedgerow removal works taking place.


If you have any questions, please do get in touch with us using the following email: project.communications@spenergynetworks.co.uk


Image 1: Phase 1 and 2 of C121 closure between 27th August and 12th October

Map of the two phases of the C121 road closure near Branxton


Crystal Rig IV update from Fred. Olsen Renewables

The Crystal Rig 4 Wind Farm is now fully operational. However, there is still work to be completed in relation to the public road and the replanting alongside the access road.

Replanting: Fred. Olsen Renewables (FOR) has been discussing replanting proposals with the Council for several months. We will continue to meet with the Council to finalise agreement on the replanting plans and hope to commence the planting of trees and hedgerows in October.

Public road status: FOR undertook significant pothole repair works on the access road in late August, these works were agreed with the Council’s Roads Department. FOR has also confirmed its “fair contribution” payment offer towards further access road updates and repairs, we await the council’s response to our offer. FOR will continue to work with the council to complete any agreed works associated with the wind farm access road.

For any further questions, please email Communities@fredolsen.com

Traffic & Travel drop-in event – October


Hosted by: East Lammermuir Community Traffic & Travel Forum (CTTF)




Tuesday 20th October 2026

Innerwick Old School / Outdoor Centre

3- 7pm


Drop-in for updates and to ask your questions about energy projects construction impacts on traffic and travel in and around East Lammermuir.

Projects being represented:

Crystal Rig IV

Branxton Substation

Eastern Green Link 1

Berwick Bank Offshore Wind Farm

Dunbar BESS (between Thistly Cross & Pitcox)

Energy Projects Traffic and Travel Drop-in at Innerwick

Newlands Hill Public Local Inquiry (PLI)

The Community Hearing date has been confirmed for this wind farm proposal, which is subject to an inquiry process due to objections from East Lothian Council.


Monday 12th October

Gifford Village Hall

7- 9pm

Find out more, including the timetable for the PLI and supporting documents on the Scottish Government Planning and Appeals Division (DPEA) website via the button below.


Image: Newlands Hill proposed windfarm site (purple dots)

Proposed Newlands Hill wind farm site shown in purple

Branxton BESS event – Correction


Zenobē has recently acquired the consented Branxton Battery Energy Storage System (BESS) project and is preparing to submit a planning application for a proposed haul road and long-term access arrangements associated with the development.


Correction – Branxton BESS Community Engagement

There was an error in the previous communication regarding upcoming community engagement events for the Branxton Battery Energy Storage System (BESS) project.

Once project timelines are confirmed, details of consultation activities and community engagement events will be shared here.


The previous advertised event at Oldhamstocks Church on Wednesday 30th September will not take place. Hopefully, there will hopefully be an event late October but details are still to be confirmed.

Project contact: Viki.McCormick@zenobe.com

Find out more via the button below.

Image: Branxton BESS site indicated in turquoise

Proposed Branxton battery storage site shown in turquoise

Energy Developments Meeting – September



Registration is now open for the annual public all stakeholder meeting for the East Lammermuir Energy Projects Partnership:


Wednesday 23rd September

Innerwick Old School / Outdoor Centre

6:30 – 9pm


Spaces are limited, so please register to attend via the button below.


”These meetings bring together representatives of the energy projects in East Lammermuir with community members, East Lothian Council and others.”


Starting with informal networking from 6:30pm and kicking off at 7pm for the main session, the main focus of the evening will be on the Principles of Community Engagement, with facilitated group activities on:

  • Working Collaboratively

  • Sharing Information

  • Listening to Concerns

  • Responding to Feedback

  • Creating a Positive Legacy


There will also be an updates on other partnership initiatives

such as the Reporting Portal.

Innerwick Old School


Marine activities off Thorntonloch Beach

Eastern Green Link 1 (EGL1)

“Marine activities off Thorntonloch Beach will support the EGL1 landfall installation works.” 

A jack-up pontoon is expected to be positioned offshore for approximately one month (August/September) subject to programme and weather conditions. This is “to facilitate marine construction activities associated with the horizontal directional drilling (HDD) landfall works and preparation of the nearshore cable corridor.”

“Supporting activities may include seabed preparation, trenching and other marine operations required to enable the installation of the subsea cable.”


Image1 Jack-up pontoon viewed from Thorntonloch beach

Jack-up pontoon seen from Thorntonloch Beach

In case you missed it…

SORELL Annual survey- Ending soon



SORELL is a local group ‘Save Our Rural East Lammermuir Landscape’ which “aims to protect and conserve the rural landscape, natural environment and historic heritage environment of the East Lammermuirs”.

It formed in opposition to the proposed Voltalia Springfield Solar Farm and BESS (Battery Energy Storage System) – over 400 acres of agricultural land close to the village of Oldhamstocks, and surrounding area including Oldhamstocks Mains and Birnieknowes.



The SORELL survey is to gauge public opinion on the renewable energy developments in East Lammermuir and how this is changing over time. It has a particular focus on the environment, roads and the Springfield Solar and BESS proposals. The online survey will be open until September 19th.

Berwick Bank Wind Farm onshore works – issued 13 August 2026

SSE Renewables have begun series of minor preparatory works at the Berwick Bank Wind Farm site ahead of the start of onshore enabling works.

These early activities will include the installation of small sections of site fencing, hedgerow management, ground investigation surveys and the establishment of a small site compound to the south of the proposed substation site.

Over the coming weeks, construction teams will begin work on a haul road to the north of the site, just south of the A1 Innerwick turn-off. In the months ahead, earthworks will also commence to prepare the land for future civil engineering works within the substation site.

We do not expect these initial activities to cause significant disruption. However, local residents may notice an increase in vehicle movements in the area as site compounds are established and works get underway.

We are committed to keeping local communities informed as the project progresses. Anyone wishing to receive future project updates can join our mailing list by emailing their contact details to berwick.bank@sse.com.

View the project site on the East Lammermuir Energy Developments map

Sign up for email updates · See previous bulletins