Energy Projects News Bulletin

Christmas wind down

19th December to 5th January


Work at the Eastern Green Link 1 convertor station site will stop for the festive period on Friday 19 December and restart on 5 January.


The Branxton Substation team will also observe the same dates, although work has not yet started on that project, as they are still discharging some planning conditions.


Fred. Olsen Renewables have confirmed that there will be no HGV’s on the road from the Crystal Rig site during this time. They will have a small build team on the site either side of Christmas and new year, which will be in either cars or small vans, but this traffic will be limited.

Connections Reform

NESO (National Energy System Operator) has published their first results from the Connections Reform process. This is a process to reorder the grid connections queue for energy projects from the old “first-come, first-served” queue, which had grown to

700GW, four times what’s needed by 2030, to a reordered “most-ready, most-needed” queue.


At this stage we only know the big picture, and not what “gate” each of the projects proposed for East Lammermuir have been allocated to (if any). We will be reaching out to developers for updates and will keep you posted as we understand the implications for East lammermuir better.


We gather that there is now a moratorium in place on new BESS projects entering the connection queue.

Confused about what the “gates” are?

Taking forward our community priorities…


NnG Community Benefits

The Neart na Gaoithe (NnG) offshore wind farm is now fully operational, and its owners have committed to providing community benefit funding of £270,000 per annum, rising with inflation, for the expected 25 year lifespan of the wind farm. Communities within the East Lammermuir Community Council area will benefit from 68% of the funding (£183,600 per annum plus inflation) for the first three years.

Community Transport News

One of our four community ambitions is that a public or community transport service should be re-introduced to link the villages with Cockburnspath and Dunbar.


We our holding a workshop on this theme on the evening of Thursday 22nd January in Stenton Village Hall (times TBC) to explore options together. Pencil in the date for now and watch this space for more details!

Energy Efficiency news

Following on from the workshop on Energy Efficiency in October, alongside Sustaining Dunbar and Insulate Innerwick’s work, you now have the opportunity over the coming weeks to have your home surveyed with a thermal imaging camera for free by a trained member of Sustaining Dunbar’s Community Heat Team.

Active Travel news

Thank you to everyone who filled in the walking and active travel survey! The results are being analysed and we will share the findings with you in the New Year.

In case you missed it…




Have your say on East Lothian Council’s Planning Department

Have you engaged with East Lothian Council’s Planning Team recently? The Improvement Service is running its annual survey of all users of planning authorities in Scotland to collect your views on the service you have received. The information provided will be used to identify areas for improvement.The survey should only take a few moments of your time, and all your responses help us improve our offer to you.


The survey is open now and closes on 9 January 2026