Branxton Substation Road Closures
from SP Energy Networks
From SPEN ‘Please be aware that the previously advertised Phase one road closure has been extended due to unforeseen circumstances and will now be in place until Friday 25th September.
Once the Phase one closure has been lifted, Phase two will be implemented and will remain in place until Monday 12th October. We apologise for any inconvenience this may cause.’
Thursday 27 August – Friday 25th September (was 13th September).
Phase one – A full road closure will be in place on the C121 between Blackcastle cottage and the junction with the U215. Please note the U215 will remain open throughout. This is detailed, along with the diversion in Image below. This will allow further junction works to be carried out where the haul road crosses the public road.
Friday 25th September (was 13th September) to Monday 12th October
Phase two – a full closure of the section of the C121 between the junction of the U215 and the existing substation will be required to facilitate utility diversion works. This is detailed in image below. The U215 will remain open throughout.
‘We would like to clarify that those living in properties around the closure site, will be able to access their properties throughout the works.’ SPEN
Update on hedgerow / tree removal plans on C121
SP Energy Networks is currently reviewing the detailed plans for the road widening works on the C121 at the entrance to the new Branxton substation. Before any decisions can be made regarding the retention or removal of trees and hedgerow, further surveys and assessment of clearance requirements are needed. As a result, no vegetation works will be undertaken before 2027. SP Energy Networks remains committed to engaging with the Community Traffic and Transport Forum (CTTF) and will review any future proposals with the group in advance of planned works.
For any questions, please email – project.communications@spenergynetworks.co.uk
Image 1: Phase 1 and 2 of C121 closure between 27th August and 12th October