Energy Projects Bulletin — 2 April 2026

Historical bulletin — originally published 2 April 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin

Eastern Green Link 1

landfall cable works update


Prysmian, cable contractor for the EGL1 project, have notified of plans for 24hr working over the summer period. All the details are available via the button and the map indicates the areas affected.

EGL1 cable landfall works area near Thorntonloch Beach

Branxton Substation enabling works update





Following discussions with the local community, a Temporary Traffic Regulation Order (TTRO) has now been agreed with East Lothian Council to cover the area around the two sets of traffic lights on Bilsdean and Dunglass bridges (U220 on the map).

The TTRO is now in place and restricts vehicles for the Branxton project to 20mph, and the lights will be operating on a series of short dates throughout April and into early May. These include:



Thursday 02 April (PM)- Friday 03 April (AM)

Monday 06 April- Tuesday 07 April (AM)

Thursday 09 April (PM)- Friday 10 April (AM)

Monday 13 April- Tuesday 14 April (AM)

Thursday 16 April  (PM)- Friday 17 April (AM)

Monday 20 April- Tuesday 21 April (AM)

Thursday 23 April  (PM)- Friday 24 April (AM)

Monday 27 April- Tuesday 28 April (AM)

Thursday 30 April  (PM)- Friday 01 May (AM)


The traffic lights in place on the C120 (see map) have been extended to accommodate additional road improvement works and will now be in place to 15th April. This delay impacts on the timing of the planned existing slip road closure, which has to wait until after the traffic lights have ended. East Lothian Council have issued a road closure notice for 30th April to 28th May for the slip road closure (details via button below). Pedestrian/cycle access will be maintained throughout.




We appreciate the community’s patience during these works and encourage people to contact the project.communications@spenergynetworks.co.uk  email address with any questions.


Image: area of impact with road numbers, X = Bilsdean site.

Map of the roads affected by the Branxton works near Bilsdean


Updates on Public Right of Way closure – A1 north side near Skateraw


2 weeks ago we received the following update from SP Energy Networks’ EGL1 project about changes to this scheduled path closure:


To facilitate the construction of haul roads, trenching, and pipework ducting, and ensure public safety, we must temporarily restrict access to the track on the north side of the A1 near Skateraw.

Periodic closure of the track is scheduled to begin on 30 March 2026 and is expected to continue until 2028.


Click the link below for more information.



We will share times and dates of closure planned for the week ahead in this bulletin, but please note that unscheduled closures could happen a short notice.


1/4 update from the project:


We don’t have any plans to close the unofficial footpath before the 14th April 2026 at present. This will be dependant on preceding tasks and could slip a day or two either way.


Image: map of impacted track

Track north of the A1 near Skateraw marked in yellow

East Lammermuir River Catchment Restoration Project

Catch up on the latest from this exciting project via the button below!


Headline news – Sustaining Dunbar are recruiting for a Catchment Restoration Development Officer, check out the role here.

Springfield Solar


The Scottish Government’s Planning and Environmental Appeals Division (DPEA) has written to everyone who submitted a response regarding the Public Inquiry that appears to have been decided upon, in connection with the Section 36 Electricity Act application for planning consent to the Energy Consents Unit (ECU). Please check your spam folders if you submitted a representation and haven’t seen this.


As soon as ELCC has more information regarding the Springfield Solar development it will be included in a future bulletin.

In case you missed it…

Aikengall Wind Farm traffic


There is currently an increase in traffic up to Aikengall wind farm, which started last week and potentially will last for another 2 weeks, due to urgent road works, it should all be daytime traffic and no more than 20 trucks, so 40 movements in total over the period.


Image: the access road is marked in green and the wind farm shown as triangles.

Access road to Aikengall in green, with wind turbines marked by triangles

Crystal Rig 1 Repower – opportunity to comment on changes to application


East Lammermuir Community Council have received updated information about the Crystal Rig 1 Rower application from the Energy Consents Unit. They have until

Tuesday 14 April to comment and would like to hear your views to inform this.


The main updates are:


  • Turbine Height Reduction:

    All ten turbines are now proposed at a maximum tip height of 200 m (reduced from a mixed layout of 200 m and 230 m).

  • Environmental Impact Assessment Updates:

    Across all technical topics- landscape and visual, cultural heritage, ecology, ornithology, hydrology/geology, aviation, noise, and traffic- the applicant concludes that no new or significant effects arise as a result of the reduced turbine heights or associated refinements.

  • Access Route Clarification:

    Additional detail has been provided on the proposed turbine delivery route, including analysis of pinch points. The applicant considers that only minor adjustments or vegetation trimming may be required, with no significant environmental, heritage, or ecological implications.


The document can be accessed via the Energy Consents Unit website by searching for ECU Reference ECU00005089. The document title is  “Application – Developer Clarification Information – 16 March 2026”.  Please send comments to info@elcc.scot by Sunday 5th April.

Energy Developments Meeting

11 March 2026


These are all stakeholder meetings for the Energy Projects Partnership, with representation from East Lothian Council, community and energy projects. We hold these meetings three times a year, twice are invite only (to get a balance in attendance between community and industry), such as this one.


Read the meeting write-up via the button below.

Taking forward our community ambitions




Our vision as an Energy Projects Partnership is for East Lammermuir to be a better place as a result of the energy developments.

Over the autumn and winter months we held a series of workshops looking at next steps for the 4 community ambitions drawn from the East Lammermuir Local Place Plan, to plan how to achieve this vision together.


We are delighted to share the reports from the workshops with you! Click the button below to explore.

Renewable energy survey results


East Lammermuir Community Council held a survey on a Unified Statement on the impact of renewables on rural Scotland. This closed on 13th March 2026 and you can view the results and next steps via the button below.


Thank you everyone who took part!


EGL1 possible road closures on the U209 / Market Road



The Eastern Green Link 1 (EGL1) project’s cable contractor is currently carrying out drilling works beneath the U209. We have received the following information to share with you:


During this operation, we have experienced some unexpected drilling fluid breakouts at the surface within fields above the drill path. Although these are being closely monitored, there is a possibility that a breakout could occur in the road verge or on the road itself. If drilling fluid were to reach the road surface, it could make the U209 unsafe for road users.


To ensure public safety, we have applied for, and received, an emergency road closure authorisation from East Lothian Council. We do not intend to close the road unless absolutely necessary. However, if any drilling fluid reaches the U209, we will be required to close the road to carry out a clean up and return the surface to a safe condition. 


This drilling operation is expected to continue until late April or early May.


The map below shows the extent of the road closure and further information can be found via the button below.

Extent of the possible U209 Market Road closure



Crystal Rig IV Traffic Alerts

Click the link below for the latest information about traffic movements from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.