Energy Projects Bulletin — 22 January 2026

Historical bulletin — originally published 22 January 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

Energy Projects News Bulletin

Branxton Substation Traffic management


Enabling works to construct a slip road off the A1 and other road works have now begun. To support this work, traffic management will be in place in the Bilsdean area on the following dates to enable them to move materials to and from site.

 

Tuesday 27th – Thursday 29thJanuary:

Traffic lights at the narrow road sections on the bridge across the Dunglass Burn and at Bilsdean Bridge.


The road effected is the U220, shown on the map.


For more information click the button below.

Map of the Dunglass Bridge and Branxton enabling works

Berwick Bank Wind Farm

Onshore Works Update

East Lammermuir Community Council are keen to hear your views on the planning application below to inform their response. They have agreed an extension to their deadline to enable this. Please send any comments to info@elcc.scot by 30th January (as well as commenting directly to East Lothian Council if you wish, as per the information below).

Green arrow marks the proposed underground cable section between landfall and the Berwick Bank onshore substation

East Lothian Council granted Planning Permission in Principle for the project’s onshore transmission infrastructure in December 2023. An application has now been submitted providing more detailed information regarding the installation of one section of underground cables (indicated by the green arrow) between the landfall and the onshore substation (orange rectangle).


Comments on the proposals are welcome and should be sent to environment@eastlothian.gov.uk by 30th January.


Find out more via the link.

Crystal Rig I Repower

This application was due to be reviewed by East Lothian Council’s Planning Committee on 13th January following their proposed objection to this application from Fred. Olsen Renewables. The decision lies with the Energy Consents Unit and ELC are a statutory consultee, but if they object it may lead to a public inquiry.


The item was removed from the agenda in the end, but the report can be viewed via the button below. We understand it will be called into a future Planning Committee meeting instead.

Crystal Rig repowering site and proposed turbine layout

Updated web portal for the Energy Consents Unit




From 16 January 2026, the Energy Consents Unit are introducing a new update to their online portal to make it easier for members of the public to submit representations on energy consent applications in Scotland.


Find out more via the button below.

Planning for energy and transmission infrastructure

NESO (National Energy System Operator) are working on various strategic and spatial plans to guide future energy infrastructure across the UK.


Check out the helpful explainer videos in the link below to find out more.

In case you missed it…


Onshore electricity generation threshold consultation


Scottish Government are seeking views

on increasing the current threshold of 50MW for onshore electricity generating stations to be considered by local authorities.



Increasing the 50MW threshold, whether for all or only some technologies, would transfer responsibility for deciding more applications to planning authorities.

The consultation will run from 30 December 2025 until 27 March 2026.


Find out more via the button below.

Berwick Bank

Offshore Wind Farm Update


SSE has successfully secured a 20-year contract for 1.4GW of low carbon offshore wind power from Phase B of its Berwick Bank Wind Farm project in the UK’s seventh Contracts for Difference (CfD) Allocation Round, announced today.

Eastern Green Link 1 Construction Update


As we move into the new year, construction activity on the EGL1 project continues to progress, with works underway across a number of areas. There will be an increase in HGV activity movements, traffic management measures and more visible signs of construction.


The map shows the converter Station site (pink box) and the planning boundary for the cable route and haul road (red outline). The blue line indicates the combined traffic management route for EGL1 and Branxton Substation.


Click the button below to read more.

Eastern Green Link 1 construction route, with the works area highlighted

Free home heat surveys

Following on from the workshop on Energy Efficiency in October, alongside Sustaining Dunbar and Insulate Innerwick’s work, you now have the opportunity over the winter period to have your home surveyed with a thermal imaging camera for free by a trained member of Sustaining Dunbar’s Community Heat Team.


Contact ellen@sustainingdunbar.org to book.