Energy Projects Bulletin — 22 October 2026

Historical bulletin — originally published 22 October 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin



BRAX BESS Innerwick Storage

Public Consultation Webinar – Thursday 22 October

Consultation webinar looking at how Innerwick Storage relates to the consented BraxBESS application.

The proposals are for updated battery energy storage infrastructure and associated works within the previously consented Braxbess Storage development (ECU Reference: ECU00004993), located south of Barns Ness Terrace, Innerwick.


​The purpose of this consultation is to provide information on Innerwick Storage, explain how it relates to the existing consented scheme, and invite comments before an application is submitted.

A public consultation webinar will be held today, Thursday, 22 October 2026 6-7pm. Details of how to join the webinar will be made available on the project website in advance of the event: See button below.

Comments can be made through the project website or by contacting the project team at innerwickstorage@pegasusgroup.co.uk .

Comments are invited until Monday, 9 November 2026.


Image Consented Brax BESS site

Proposed BraxBESS site marked in purple

Update on Springfield Public Legal Inquiry


“On 16 October 2026 the Reporters ruled that the proposed Bowshiel Solar Farm is not to be regarded as part of the Springfield Solar Farm & BESS application for Environmental Impact Assessment (EIA) purposes, and for the purpose of the public inquiry.

The Reporters do not require further information about Bowshiel, or its grid connection, on the basis that the two solar farms form a single EIA project, nor do they presently consider a mandatory cumulative assessment of Bowshiel’s connection to be required.

Nonetheless, the ruling expressly treats evidence concerning potential cumulative effects of the Bowshiel connection as relevant to the inquiry.”

Chris Bruce

Chair – East Lammermuir Community Council

Image 1 Springfield Solar Farm & BESS (in Planning)

Image 2 Bowshiel Solar Farm, both by Voltalia

Springfield solar site marked in pink
Springfield solar project location south of Dunbar




SPRINGFIELD SOLAR & BESS

Community Consultation events



The public is able to make comment on additional information on Voltalia’s Springfield application up until 30 October 2026 at events organised by the Lammermuir Alliance.


“Who are the Lammermuir Alliance?

The Lammermuir Alliance is a coalition of Oldhamstocks Community Association, East Lammermuir Community Council, Cockburnspath and Cove Community Council, and Save Our Rural East Lammermuir Landscape (SORELL).

The Alliance has come together to oppose the proposed Springfield Solar Farm and BESS at the Local Public Inquiry, and to help ensure that the concerns and interests of local communities are represented throughout the inquiry process.


The Alliance would like to make local residents aware that additional environmental information has now been submitted in connection with Voltalia UK Ltd’s proposed Springfield Solar Farm.

The proposal includes:

  • Up to approximately 165 MW of solar PV generation

  • Up to approximately 80 MW of Battery Energy Storage (BESS)

  • Associated infrastructure, access and landscaping


The newly submitted information considers the cumulative effects of the development alongside:

  • the proposed Springfield Collector substation within the site; and

  • the proposed transmission connection between the Springfield Collector and Branxton Substation, around 1km to the north-west.”


This is a reminder that you can still view the documents and prepare a response at two locations:

This is a reminder that you can still view the documents and prepare a response at two locations:

1.      The foyer of Cockburnspath Village Hall (times vary)

2.      Dunbar Library (opening hours Dunbar Library | East Lothian Council)

The information can also be accessed online at the DPEA Planning Appeals website (NB it also has 4 appendices) at the DPEA link below: see published items 28 September 2026

Representations should:

  • quote reference BES–210-1

  • be submitted by email to claire.murray2@gov.scot or by post to Environmental Appeals Division, Hadrian House, Business park, Calendar Road, FKI IXR.  

Representatives of Cockburnspath & Cove Community Council, East Lammermuir Community Council, Oldhamstocks Community Association and SORELL will be present and able to assist on:

  • Sat 24 Oct 10.00 a.m. – 12.00 p.m. Dunbar Library & Mtg Rm 1 Bleachingfield Centre  – last of three

Beth’s blog – delivering the Local Place Plan


Check out Beth Landon’s latest blog post via the button below.

Two participants in the Local Place Plan story


Energy Developments Meeting September 2026



At the 2026 annual public meeting of the Energy Projects Partnership on Wednesday 23 September, attendees took part in group work looking at the East Lammermuir Principles of Community Engagement.



Feedback from the groups has been collated and analysed and is available in the short report via the button below. Grab a cuppa and check it out!

Discussion at the community engagement meeting

Energy Projects Traffic and Travel Drop-in October 2026


The Community Traffic and Travel Forum’s drop-in event took place on Tuesday 20th October in Innerwick Outdoor Centre, with 20 residents attending and lots of feedback that people had been able to find out the information they were looking for.

Find out more via the button.

Energy Projects Traffic and Travel Drop-in poster


In case you missed it…


Newlands Hill Public Local Inquiry (PLI)

Full hall for Community Hearing



The Newlands Hill DPEA hearings are available online, on YouTube. The Community Hearing from Monday is here with ELCC Chair Chris Bruce speaking at 1:35 til 1hr:42mins.


This wind farm proposal is subject to an inquiry process due to objections from East Lothian Council.


“This week sees the Public Inquiry into the proposed Newlands Hill Energy Hub.  This is taking place in Gifford Village Hall.  The Community Hearing on Monday evening was so well attended that perhaps 30 folk were turned away as the fire regulations limit for the hall had been reached.

East Lammermuir was represented by several residents and the Chair of the Community Council.  The various hearings continue until Thursday, 15 October, concluding with a discussion about Planning Conditions to be imposed should the development be consented.  

East Lammermuir CC neither supports or objects to the proposal as the survey carried out at the point the planning application was submitted (end of 2023) showed an exact 50:50 split in support or objection from local residents living in East Lammermuir.”

Chris Bruce

Chair, East Lammermuir Community Council


Vice Chair for Dunpender CC, Allison Cosgrove was amongst those who were turned away, but the event was available online.


” The hall was so packed when we got there that we were unable to get in – around 30 people were turned away. However, it was live streamed so we could watch it when we got home.”


Find out more, including the timetable for the PLI and supporting documents on the Scottish Government Planning and Appeals Division (DPEA) website via the button below.


Image: Newlands Hill proposed windfarm site (purple dots), with proposed HGV access route in brown.

Map of the Newlands Hill proposal

Dunbar BESS planning update

(consented project)



“FRV Powertek has submitted an application to East Lothian Council (ELC) to keep an existing field access open. This is not a new site access. This is separate to the BESS access, which would remain as previously approved. The approved BESS access was previously reviewed by both West Barns and East Lammermuir Community Councils, approved by East Lothian Council as local planning authority, and deemed acceptable from a highways perspective by the local highway authority. The local highway authority has also confirmed in principle that the retention of the existing field access is acceptable.

The determination deadline for the application is 23 November. Further information is available on the ELC Planning Portal under reference 26/00947/P (or via the button below). We remain committed to community engagement on the Dunbar BESS project and welcome questions or feedback.” FRV Powertek


Project contact: mike.clements@frvpowertek.com

ELC planning contact: environment@eastlothian.gov.uk