Energy Projects Bulletin — 26 June 2025

Historical bulletin — originally published 26 June 2025

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

Energy Projects News Bulletin

Updates on roads and an invitation!

Community Benefits event – 14 July

The poster advertised an East Lammermuir Community Council discussion on whether community benefits should be mandatory and what should happen next locally. It welcomed everyone without booking, from 7 to 8.30 pm on Monday 14 July 2025 at Innerwick Old School, Barns Ness Terrace. The website printed on the poster was elcc.scot/energydevelopments. The invitation in this edition names Innerwick Village Hall. The 3 July bulletin announced the change to Innerwick Old School.

An invitation from Chris Bruce,

Chair of East Lammermuir Community Council


Dear fellow-resident


On 10 March this year the community council hosted a first community conversation about the use of community benefits we are likely to see from the electricity infrastructure that gets built in our patch.  About twenty people joined in. That discussion helped us to create 
the proposal that the developers have now accepted for focussing financial benefits on four local priorities – from our Local Place Plan. These four priorities were confirmed by the community at the public Energy Developments meeting on 19 May.


Working with Foundation Scotland, we are holding a follow-up discussion on 14 July.  It will talk about the current Government consultation on community benefits – and how that might affect us.


Please join us to further the discussions! Innerwick Village Hall, 19.00 – 20.30 Monday 14 July.


Kind regards

Chris


chair@elcc.scot 

Innerwick road closure

C121 Barns Ness Terrace


This is a Prysmian (SPT contractor) related road closure and

is scheduled to begin on 30th June and run until 11th July. Please note that these dates are not yet confirmed, as Prysmian are awaiting final approval from East Lothian Council under permitted development.

Advance warning signs were installed on 9th June, following approval of the necessary road closure paperwork (TTRO) on 6th June. As part of this process, notices have also been published in local newspapers.

 

Click the link below for a map showing the diversion routes for the upcoming closure.

Crystal Rig IV Wind Farm Escorted Deliveries

Mid-June to end of August


Fred. Olsen Renewables have advised that abnormal loads are being escorted under police escort overnight. The road is not being closed.


The access road is marked in turquoise on the map below and the wind farm under construction is the pink dots.


Click the button below for more details and to sign up for traffic alerts.

The delivery route leaves the A1 north of Innerwick, passes west of the village and runs southwest towards Dunbar Common. The Crystal Rig IV turbines are marked farther south.

Sign up for email updates · See previous bulletins