Updates on Public Right of Way closure – A1 north side near Skateraw
Last week we received the following update from SP Energy Networks’ Eastern Green Link 1 project about changes to this scheduled path closure.
To facilitate the construction of haul roads, trenching, and pipework ducting, and ensure public safety, we must temporarily restrict access to the track on the north side of the A1 near Skateraw.
Periodic closure of the track is scheduled to begin on 30 March 2026 and is expected to continue until 2028.
Click the link below for more information.
We will share times and dates of closure planned for the week ahead in this bulletin, but please note that unscheduled closures could happen a short notice.
25/3 update:
We are slightly behind schedule, so we have no plans to close the footpath between Skateraw and the A1 for the next two weeks.
Image: map of impacted track