Energy Projects Bulletin — 28 August 2025

Historical bulletin — originally published 28 August 2025

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

Energy Projects News Bulletin

Crystal Rig IV: Base Construction Complete

Fred. Olsen Renewables have just announced the completion of all the bases for the wind turbines across their Crystal Rig IV site.


The map shows the existing Crystal Rig sites (green, blue and yellow dots) and the new CRIV site currently under construction (pink dots)


Find out more and watch their video by clicking the button below.

Southwest of Innerwick and Oldhamstocks, the new Crystal Rig IV turbines lie along the southern edge of the existing turbine groups.

EGL1 Temporary Path Closures Update

Contractors for the Eastern Green Link (EGL1) project have erected fencing along their cable route, including a recent further 150m section at the location indicated by the bright red line on map (the darker red line is the EGL1 onshore works boundary).

Double gates have also been installed (location indicated in the 2nd photo).

There will be no further path closures until 2026 and 4 week’s notice will be given for periods when public access to the path will be temporarily restricted for safety reasons.


Check out the Energy Developments map to zoom out!

(CDM Fence = Construction (Design and Management) regulations fencing)

The bright red section of EGL1 fencing lies in the field between the A1 and Dry Burn, close to the road.
The 150-metre fence follows the wall between the existing gate at the construction fence and the double-gate location on the track beside the A1.

Traffic Alerts

Click the links below for the latest information about construction traffic movements.

In case you missed it…

Eastern Green Link 1 (EGL1) Park and Ride

Through Metlen, one of the contractors involved in the EGL1 project, a planning application is expected to be soon submitted to East Lothian Council for a Park and Ride facility, located on vacant development land within Dunbar Business Park, to the east of Dunbar Garden Centre and adjacent to the East Coast Main Line. This is being done with the aim of minimising the local traffic impact of workers who will be working on the EGL1 site over the coming years.

 

In advance of the planning application, the attached letter has been sent to residents in the immediate area, including an explanation of the application, and a map showing the proposed location of the site.

Response to UK Government paper on mandating community benefits and shared ownership of renewables

East Lammermuir Community Council has submitted a response to the UK Government working paper on Community Benefits and Shared Ownership of Low Carbon Energy Infrastructure, informed by the community meeting held on 14th July.


ELCC have also joined 45 organisations across Scotland as a signatory to an open letter to UK Government in response to this working paper.


Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.