Energy Projects Bulletin — 28 May 2026

Historical bulletin — originally published 28 May 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin

Monitoring of planning conditions


When an energy development is consented, planning conditions are applied setting out rules for how development must take place in a way which minimises impact on the community, environment, access, roads and in many other aspects.

But how are planning conditions monitored and enforced and how can local residents report any issues or breaches?

The Energy Projects Partnership has compiled these “frequently asked questions” with input from developers, transmission owners and East Lothian Council, which we hope you will find helpful.

Overnight Resurfacing at A1 South of Innerwick Junction

BEAR Scotland, on behalf of Transport Scotland will be undertaking essential overnight carriageway resurfacing on the A1 in both directions, south of Innerwick Junction over 19 nights from Monday 8th June to Thursday 2nd July, from 19:30 to 06:00 each night. No works are currently planned for Saturday or Sunday nights.

Traffic restrictions: The A1 will remain open, however a 10mph convoy traffic management setup will be in place in both directions. The A1 southbound dual carriageway will be restricted to a single lane on approach to the site during the works.


Road users looking to head South on the A1 from the Innerwick Junction are to follow the A1 Northbound to Spott Roundabout and return on the A1 Southbound (blue route).

A1 resurfacing and diversion route south of Innerwick Junction

Intermittent closures of U209 (Market Road)

Road closed from its junction with C122 to its junction with C124. Closure to be in place as and when required for no more than an hour at a time between Monday 1st June and Wednesday 3rd June 2026.


Image: Map of impacted road

U209 Market Road works location


Path closure – A1 north side near Skateraw


SP Energy Networks’ EGL1 project have issued these notices:


Path opening times this week – Week of 25 May

There are no plans to temporarily close it this week. The path on the north side of the A1 near Skateraw remains open.


Path opening times next week – Week of 1 June

Due to the upcoming work schedule, the path on the north side of the A1 near Skateraw will close a few days earlier than advertised in the previous update (issued on Monday to the relevant subgroup of subscribers to this bulletin).

  • The path will remain open all day Monday 1 June and Tuesday 2 June.

  • The path will then close from 7am on Wednesday 3 June.

  • The path will remain closed until further notice.


For information

  • Safety is our priority. Due to the heavy machinery and work involved, it is not possible to provide a date as to when the path will reopen at this time. We remain committed to temporarily reopening the path throughout the two-year period whenever it is safe to do so. We apologise for the inconvenience and appreciate your understanding during this period of disruption.

  • We expect to close the path on some weekends by exception depending on the works schedule. We will continue to share an update for the Energy Projects News Bulletin each week.

  • It is not possible to provide a safe alternative diversion for this path because the site is positioned between active construction and the A1. Discussions are ongoing with East Lothian Council. We apologise for the inconvenience and appreciate your understanding during this period of disruption.


East Lothian Council Access Officer has confirmed this is Public Right of Way

and is actively challenging this path closure.


Image 1: map of impacted track

Image 2: South end of Path closure

Track north of the A1 near Skateraw marked in yellow
South end of the path closure near Skateraw

Aikengall Wind Farm update



CWP Energy have some HGV movements planned for the next two weeks

starting May 20th and continue until early June.

The times will be varied however, in total, they expect there will be 36 HGV truck movements (total number of journey to and from site).



Image 1: map of road from A1 to Aikengall

Route from the A1 to Aikengall wind farm

Berwick Bank Windfarm

Variation application (offshore element of project)


Berwick Bank Wind Farm Limited have submitted an application to the Scottish Ministers for a variation to the existing section 36 consent granted on 31 July 2025. The application documents are available for review and comments can be sent to MD.MarineRenewables@gov.scot by 18 June 2026


The variation request is to:

  • Allow for the discharge of conditions for each proposed phase of the Development of the Berwick Bank Wind Farm, as opposed to the development as a whole and;

  • To correct discrepancies in the co-ordinates included in the offshore transmission infrastructure (part 1) and offshore transmission infrastructure (part 2) marine licences.

The section 36 consent and marine licence variation applications, and supporting documentation can be accessed via the link in the button.

Branxton Substation enabling works





The temporary traffic lights across the Bilsdean and Dunglass bridges (U220 on the map) will be operating on a series of short dates throughout  May, with a 20mph zone along this road in place until 31 May. These include:



Thursday 29 May  (PM) – Friday 30 May (AM)


The existing slip road closure (C120 junction with A1, see map) is still planned to be lifted on Friday (details via button below). Pedestrian/cycle access will be maintained throughout.




SPEN appreciate the community’s patience during these works and encourage people to contact the project.communications@spenergynetworks.co.uk  email address with any questions.


Map and Image 1: extent of 20mph zone

Image 2: Closed end of U220 Bilsdean

Map and aerial view of the 20 mph zone on the U220 at Bilsdean

In case you missed it…

Lorries in our Lanes (LIOL)


Thanks to everyone who attended our LIOL meeting in Innerwick on Monday night, hosted by the Community Traffic and Travel Forum.  These meetings offer a space to hear updates on construction traffic and travel impacts from energy project representatives, with time for questions from the community.



Archive note: The presentation from the Lorries in Our Lanes meeting on 18 May 2026 is no longer available at its original address.

Presentation at the Lorries in our Lanes meeting

Community Development Officer


Job opportunity –  Application deadline 15 June 2026


East Lothian Climate Hub have been invited by East Lammermuir Community Council to host a Community Development Officer role, to lead on coordination of delivery of our 4 community ambitions in East Lammermuir. Our priority areas from the Local Place Plan are themed around biodiversity, active travel, energy efficiency in homes and community transport.


Click on the button for full details and job description. Please share!



We have also just published the 5th report following the workshops, looking at synergies and efficiencies to deliver the 4 community ambitions which were focused on in the workshops. These reports will guide the work of the Community Development Officer. Check it out via the button.



Crystal Rig IV Traffic Alerts

Click the link below for the latest information about traffic movements from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins