Energy Projects Bulletin — 4 June 2026

Historical bulletin — originally published 4 June 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin


NnG Community Fund awards



The latest round of awards from the Neart na Gaoithe (NnG) Community Fund in East Lammermuir has been announced in a press release (view via the button). Awards were made for an East Lammermuir Community Development Officer post, hosted by East Lothian Climate Hub (ELCAN), and Lothian Heat’s Warm Homes project, also with an East Lammermuir remit.

Ellen Abbi is now in post as the Warm Homes Project Officer (contact: ellen.abbi@lothianheat.org) and ELCAN are currently recruiting for a Community Development Officer (see below).

Find out more about the fund on the Foundation Scotland website.

Image: Ellen Abbi, Warm Homes Project Manager

Ellen Abbi, Warm Homes Project Manager

Community Development Officer


Job opportunity –  Application deadline 15 June 2026


East Lothian Climate Hub have been invited by East Lammermuir Community Council to host a Community Development Officer role, to lead on coordination of delivery of our 4 community ambitions in East Lammermuir. Our priority areas from the Local Place Plan are themed around biodiversity, active travel, energy efficiency in homes and community transport.


Click on the button for full details and job description. Please share!



Eastern Green Link 1 (EGL1)

Intermittent closures of U209 (Market Road)


The EGL1 team have let us know about traffic management works scheduled on 10 June to facilitate strimming in the verge. This will be on the U209 – Market Road (just past the Prysmian compound as you come off the A1 into Innerwick). It is anticipated this will only take 1hr however the TTRO has been granted by East Lothian Council to be used all day if required.



SP Energy Networks apologise for any inconvenience but hope this will be kept at an absolute minimum.


Image: Map of impacted road

U209 Market Road works location

EGL1 coastal works near Thorntonloch Beach


Starting 6 June through 29 July, works relating to casing installation and fusion welding will commence near the Torness shoreline. To ensure the project remains on schedule, these works will operate 24 hours a day, 7 days a week. Dates are subject to change.

 

  • Daytime: Focus on casing installation along the cable route.

  • Nighttime: Welding activities, including work under the railway crossing.

 

Prysmian (cable contractor) is committed to minimising disruption. Noise levels will remain below 96 dB(A), comparable to a lawnmower, and silenced generators will be utilised at night. To ensure safety and visibility, 20 light towers will be active; however, these will be directed inward to prevent glare on the railway and highway.


Path closure – A1 north side near Skateraw


SP Energy Networks’ EGL1 project have issued these notices:


Path opening times  – Week of 1 June


  • The path has been closed today Thursday 4 June (the path closure this morning was delayed last-minute due to mobilisation delays).

  • The path will remain closed until further notice, including weekends.


For information

  • Safety is our priority. Due to the heavy machinery and work involved, it is not possible to provide a date as to when the path will reopen at this time. We remain committed to temporarily reopening the path throughout the two-year period whenever it is safe to do so. We apologise for the inconvenience and appreciate your understanding during this period of disruption.

  • We will continue to share an update for the Energy Projects News Bulletin each week.

  • Because the site is positioned between active construction and the A1, unfortunately it is not possible to provide a safe alternative diversion for this path.


East Lothian Council Access Officer has confirmed this is Public Right of Way

and is actively challenging this path closure.


Image: map of impacted track

Path near Skateraw marked in yellow

EGL1 contact: project.communications@spenergynetworks.co.uk

Branxton Substation enabling works






To complete the new A1 slip road the temporary traffic barrier must be removed to tie in the new road. This requires night shift working from 16th to 18th June. Works will be completed as quickly as possible, and steps will be taken to minimise noise.



Forthcoming works include progressing the 3km haul road to the Branxton substation site, which crosses public roads at three locations.  To support construction of these junctions (including signage, road widening and resurfacing), road closures have been agreed with East Lothian Council as follows:  

  • Location 2: Lawfield Road – 11th June to 5th July

  • Location 3: ZU215 – 4th to 27th August

  • Location 4:C121 – 19th August to 13th September

  • C121 road widening requires a closure at Location 5: 14th September to 12th October


As construction on the project continues, we will continue to carefully phase activities to minimise disruption and work closely with the community – ensuring residents are kept informed. 




SPEN appreciate the community’s patience during these works and encourage people to contact the project.communications@spenergynetworks.co.uk  email address with any questions.


Image: locations of upcoming road closures (location 1, existing A1 slip road – now reopened)

Aerial view of the Branxton road closure locations

Berwick Bank Windfarm

Variation application (offshore element of project)


Berwick Bank Wind Farm Limited have submitted an application to the Scottish Ministers for a variation to the existing section 36 consent granted on 31 July 2025. The application documents are available for review and comments can be sent to MD.MarineRenewables@gov.scot by 18 June 2026


The variation request is to:

  • Allow for the discharge of conditions for each proposed phase of the Development of the Berwick Bank Wind Farm, as opposed to the development as a whole and;

  • To correct discrepancies in the co-ordinates included in the offshore transmission infrastructure (part 1) and offshore transmission infrastructure (part 2) marine licences.

The section 36 consent and marine licence variation applications, and supporting documentation can be accessed via the link in the button.

In case you missed it…

Monitoring of planning conditions


When an energy development is consented, planning conditions are applied setting out rules for how development must take place in a way which minimises impact on the community, environment, access, roads and in many other aspects.

But how are planning conditions monitored and enforced and how can local residents report any issues or breaches?

The Energy Projects Partnership has compiled these “frequently asked questions” with input from developers, transmission owners and East Lothian Council, which we hope you will find helpful.

Overnight Resurfacing at A1 South of Innerwick Junction

BEAR Scotland, on behalf of Transport Scotland will be undertaking essential overnight carriageway resurfacing on the A1 in both directions, south of Innerwick Junction over 19 nights from Monday 8th June to Thursday 2nd July, from 19:30 to 06:00 each night. No works are currently planned for Saturday or Sunday nights.

Traffic restrictions: The A1 will remain open, however a 10mph convoy traffic management setup will be in place in both directions. The A1 southbound dual carriageway will be restricted to a single lane on approach to the site during the works.


Road users looking to head South on the A1 from the Innerwick Junction are to follow the A1 Northbound to Spott Roundabout and return on the A1 Southbound (blue route).

A1 resurfacing and diversion via Spott Roundabout



Crystal Rig IV Traffic Alerts

Click the link below for the latest information about traffic movements from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.