Newlands Hill Wind Energy Hub

Public Local Inquiry


The Newlands Hill Planning Application has now moved to the Department of Planning and Environmental Appeals (DPEA) and is moving through the Public Local Inquiry (PLI) process. The first step, a Pre-Examination Meeting (PEM), will take place on Friday 6th March at 10am.


At this meeting, the DPEA Reporter will meet with Belltown, the East Lothian Council, and any other parties taking part in the PLI to determine the timings and procedures for the Inquiry process, which is likely to take place in the Summer 2026.


The meeting will be live streamed and can be accessed via the link below.


Notice of Public Right of Way closure – A1 north side near Skateraw

SP Energy Networks have issued the following statement regarding a notice that has been put up by their cable contractor, Prysmian, at this site of this proposed path closure.


We are aware of the public notice regarding the proposed temporary closure of the path North of the Innerwick junction from 30th March. The (EGL1) project team recognises the importance of this route to local residents and understands the level of concern arising from the notice.

The project team is currently reviewing the information that has been issued and is seeking further clarification on the access requirements associated with the planned works. Once we have this detail, we will be able to confirm the position and provide clear information to the community.

A further update will be shared as soon as the relevant details have been fully understood

We appreciate the community’s patience while we work through this.


Image: a replication of the image from the posted notice indicating the section of path to be closed.

Section of path near Skateraw marked for closure in red

Branxton Substation enabling works



Construction work continues at Bilsdean junction and the new slip road from the Northbound A1 carriageway.


Traffic lights are also in place on the C120 until w/c 16th March to support a contraflow system to keep the road open. The existing slip road will then close, until the start of April for installation and resurfacing works.



Contact email:
project.communications@spenergynetworks.co.uk


Image: Area of C120 traffic lights. For detailed maps click the links below.


C120 traffic lights near Bilsdean marked with a green circle

Blackcastle Cottages Road Closure



We have received notification from East Lothian Council about a road closure on the C121, from 9th to 16th March. Work will not exceed 5 consecutive days within these dates.


Confused about road numbers? Go to the East Lammermuir Developments map and select the “Roads” map layer (scroll down to the bottom of the list!) and the road numbers will show on the map.


Map of the C122 roadworks between the A1 and Innerwick


East Lammermuir Features in an article about the “Great Grid Upgrade”

by Local Storytelling Exchange.


In case you missed it…

Active Travel update


Following on from the Active Travel workshop in November, the Walk Wheel Cycle Trust are currently undertaking a Feasibility Study looking at potential crossing locations of the A1 in East Lammermuir. They have provided this update:


The team have been on site recently and our engineering colleagues are currently exploring options at four locations and the infrastructure that these would require. We are also looking into the infrastructure that would be required to allow connectivity into the National Cycle Network (NCN) and the local road network as part of this.


Trust ecologists are due on site within the coming weeks to conduct a Preliminary Ecological Survey which will help guide the options available to us.


We are also in discussions with Energy Companies, East Lothian Council, East Lothian Climate Hub and other organisations with an interest in the area to pursue any possible collaboration between ongoing projects.

Guidance on Community benefits


There is work going on in both Westminster and Holyrood to consider what Community Benefits should be made available to local communities like ours where renewables infrastructure is built.  As part of that, Scottish Government has published a Working Paper on Refreshing the Good Practice Principles for Community Benefits from Onshore Renewable Energy and you can see it at this link. There is opportunity to comment until 25 March.


Onshore electricity generation threshold consultation


Scottish Government are seeking views

on increasing the current threshold of 50MW for onshore electricity generating stations to be considered by local authorities.



Increasing the 50MW threshold, whether for all or only some technologies, would transfer responsibility for deciding more applications to planning authorities.

The consultation will run from 30 December 2025 until 27 March 2026.


Find out more via the button below.



Crystal Rig IV Traffic Alerts

Click the link below for the latest information about traffic movements from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.