Energy Projects Bulletin — 7 May 2026

Historical bulletin — originally published 7 May 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin

Welcome to our new Warm Homes Project Manager



Hello! My name is Ellen Abbi, and I am the new Warm Homes Project Manager for the East Lammermuir Community Council area.
Last winter, I enjoyed meeting a number of East Lammermuir residents whilst carrying out thermal imaging as part of the Community Heat Team alongside Sustaining Dunbar. My new role is with Lothian Heat, a community interest company, which has been appointed by East Lammermuir Community Council to deliver the community’s stated ambition for warmer and more energy efficient homes. Lothian Heat’s aim is to ensure that “no heat is wasted and no home is cold”.
I look forward to meeting many more of East Lammermuir’s residents in the coming weeks and months to help achieve these aims, so please stay tuned.

Ellen Abbi, Warm Homes Project Manager

East Lothian Planning Committee seeks more detail on repowering of Crystal Rig I windfarm


Committee members debated an application from Fred. Olsen Renewables Ltd, for the repowering of Crystal Rig I wind farm, on Tuesday 5th May.

East Lammermuir Community Council was represented at the planning committee meeting, and made a statement about the ongoing use of the access road.

Find out more via the button below.

Innerwick Village Hall renovations continue



Work inside Innerwick Village Hall, funded by Crystal Rig III community benefits (provided by Fred. Olsen Renewables), continues as East Lammermuir Community councillor, Suzie Fletcher, popped in for a progress meeting this week.

Local resident Suzie commented how local consultations on the kitchen had been very helpful and that the back room is now taking shape. There have been some stops and starts in the last few weeks due to moving the power supply and a few recommendations being considered, but things should be moving at pace over the summer. It is hoped that the Hall renovations will be complete in late summer/early autumn.  

We are also grateful to BeGreen who have funded the insulation.


Image 1: Exposing beautiful cross beams in the ceiling (credit Suzie Fletcher)

Scaffolding beneath exposed roof beams inside Innerwick Village Hall

Lorries in our Lanes

Monday 18th May

Innerwick Outdoor Centre / Old School

6:30 – 8:30pm



Join the Community Traffic and Travel Forum for updates on construction traffic and travel impacts from the energy projects.


Spaces limited, booking essential.

Find out more and book via the button below.

Branxton Substation enabling works





The temporary traffic lights across the Bilsdean and Dunglass bridges (U220 on the map) will be operating on a series of short dates throughout April and into May, with a 20mph zone along this road in place until 31 May. These include:



Thursday 07 May (PM) – Friday 08 May (AM)

Monday 11 May – Tuesday 12 May(AM)

Thursday 14 May  (PM) – Friday 15 May(AM)

Monday 18 May – Tuesday 19 May (AM)

Thursday 21 May  (PM) – Friday 22 May (AM)

Monday 25 May – Tuesday 26 May(AM)

Thursday 29 May  (PM) – Friday 30 May (AM)


The existing slip road (C120 junction with A1, see map) is now closed until 28th May (details via button below). Pedestrian/cycle access will be maintained throughout.


06 May update:


“With the traffic lights being removed [from the C120, road to Birnieknowes] we have re-enforced to the drivers that they are joining live traffic and are checking when the road markings will be installed to govern this give way.

On the U220 we are currently backfilling the track where the bus stop was, once finished the barriers will be moved back to widen the road again [see image]. These works are to support the long-term junction traffic lights and 2 way traffic.” SPEN




SPEN appreciate the community’s patience during these works and encourage people to contact the project.communications@spenergynetworks.co.uk  email address with any questions.


Map and Image 1: extent of 20mph zone

Image 2: U220 Bilsdean (SPEN)

Map and aerial view of the 20 mph zone on the U220 at Bilsdean
Temporary barriers along the U220 at Bilsdean


Path closure – A1 north side near Skateraw


SP Energy Networks’ EGL1 project have issued these notices:

To facilitate the construction of haul roads, trenching, and pipework ducting, and ensure public safety, we must temporarily restrict access to the track on the north side of the A1 near Skateraw.

Periodic closure of the track  is expected to continue until 2028.


07 May update:

The path is still scheduled to be open every weekend. The path remains closed on weekdays. The path will be opened every Friday at 3pm and closed every Monday at 7.30am.

We do expect we will need to close it some weekends by exception depending on the works schedule. We will provide advanced notice of any changes, via local updates. We are committed to reopening the route throughout the two-year period whenever it is safe to do so.


East Lothian Council Access Officer has confirmed this is Public Right of Way

and is actively challenging this path closure.


Image 1: map of impacted track

Track north of the A1 near Skateraw marked in yellow

In case you missed it…

Berwick Bank Wind Farm – planning update

SSE Renewables have submitted a detailed application to East Lothian Council regarding their substation. This is the second of three applications providing further detail, following their planning permission which has been granted in principle for the onshore infrastructure.


Click on the button below for more information and a link to review and comment on the application. Deadline for comments is 22 May to environment@eastlothian.gov.uk

EGL1 offshore works news



Over the coming period, some preparatory marine works are to take place at the Scottish Landfall as part of the Eastern Green Link 1 project. The main activity will involve checks of the seabed to confirm it is clear of any unexploded ordnance from historic use of the area. These checks are routine for offshore infrastructure projects and are designed to make sure later construction activities can be carried out safely. The works are short‑term, localised and carefully managed, with ongoing coordination to reduce any effects on other sea users.

In parallel, preparations will continue for the underground cable landfall works, which use a specialist drilling method known as horizontal directional drilling (HDD). This approach allows cables to be installed beneath the seabed and shoreline without the need for open excavation, helping to protect the coastline and reduce disturbance. Any associated marine activity will be limited and planned in advance, with environmental controls in place and clear communication as works progress.


Check out where this project makes landfall south of Thorntonloch beach on the map via the button:

Beth’s first year




It’s been just over a year now that Beth Landon has been in post as Energy Projects Partnership Manager.

Many of you will been alongside Beth in meetings, got to know her out and about, read her blogs or heard from others about the work she’s doing to support the community’s ambition that East Lammermuir is left a better place as a result of all the energy projects in process.

For Beth it’s very much been a year of finding her way with great support from many of you but there’s been no blue print about how to do the role. As the host employer, Foundation Scotland would really appreciate any observations, feedback or reflections any of you might have about how you’ve experienced the role, the difference you think it’s beginning to make and opportunities for improvement.

Whether you’re an East Lammermuir resident, an East Lothian council staff member, in the energy industry or a member of another organisation connected with East Lammermuir and in receipt of this bulletin, and if you have a spare few minutes please do share your reflections here by 15 May.



Crystal Rig IV Traffic Alerts

Click the link below for the latest information about traffic movements from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.