Energy Projects Bulletin — 8 October 2026

Historical bulletin — originally published 8 October 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin

Eastern Green Link 1

“A significant milestone has been reached at the Eastern Green Link 1 (EGL1) converter station site at Oxwellmains, with steel erection now underway.

Steelwork is being erected for the service building, which will house essential equipment including power supplies, cooling plant, and the control and protection systems.

Towards the end of the month, some larger steel girders will start to be transported to site under police escort due to the width and length of the loads. Road users will still be able to overtake these vehicles as normal, where it is safe to do so.”

SP Energy Networks

Project contact: contact@easterngreenlink1.co.uk

Image: converter station site indicated by the pink box, EGL1 planning boundary in red.

Dunbar battery storage site near the A1

Dunbar BESS planning update

(consented project)



“FRV Powertek has submitted an application to East Lothian Council (ELC) to keep an existing field access open. This is not a new site access. This is separate to the BESS access, which would remain as previously approved. The approved BESS access was previously reviewed by both West Barns and East Lammermuir Community Councils, approved by East Lothian Council as local planning authority, and deemed acceptable from a highways perspective by the local highway authority. The local highway authority has also confirmed in principle that the retention of the existing field access is acceptable.

The determination deadline for the application is 23 November. Further information is available on the ELC Planning Portal under reference 26/00947/P (or via the button below). We remain committed to community engagement on the Dunbar BESS project and welcome questions or feedback.” FRV Powertek


Project contact: mike.clements@frvpowertek.com

ELC planning contact: environment@eastlothian.gov.uk


Pitcox BESS Planning Update

Comment from ELCC


“This development is over the road from the consented Dunbar BESS on which West Barns Community Council are taking the lead.

It will be important to understand how the construction and biodiversity impacts of the two developments will interact.

East Lammermuir Community Council will be seeking involvement in the final agreed planning conditions – including the Construction Traffic Management Plan and Public Access Management Plan – primarily to ensure engagement with local community members to make sure these plans make use of local intelligence and expectations.” ELCC Chair Chris Bruce


“Following East Lothian Council’s objection in August 2025 to the Section 36 Pitcox BESS proposal, the applicant, Abei Energy, submitted additional information in response to the concerns raised by the Council. This included further information relating to landscape and visual impact assessment, hedgerow loss, cumulative noise impacts, surface water flooding and flood protection, and site access arrangements.

In June 2026, the Council withdrew its objection, having concluded that the matters which formed the basis of the objection had been adequately addressed.” East Lothian Council


Image 1 Pitcox BESS proposed site in blue, Dunbar BESS consented site in green

Image 2 – close up of sites

Pitcox battery storage project location
Detail of the proposed Pitcox site and access


Events in October…

Newlands Hill Public Local Inquiry (PLI)


The Community Hearing date has been confirmed for this wind farm proposal, which is subject to an inquiry process due to objections from East Lothian Council.


Monday 12th October

Gifford Village Hall

7- 9pm

Find out more, including the timetable for the PLI and supporting documents on the Scottish Government Planning and Appeals Division (DPEA) website via the button below.


Image: Newlands Hill proposed windfarm site (purple dots), image updated to show the proposed HGV access route in brown.

Newlands Hill project map

Traffic & Travel drop-in event


Hosted by: East Lammermuir Community Traffic & Travel Forum (CTTF)




Tuesday 20th October 2026

Innerwick Old School / Outdoor Centre

3- 7pm

Drop in for updates and to ask your questions about energy projects construction impacts on traffic and travel in and around East Lammermuir.

Project representatives and members of the Community Traffic and Travel Forum will be there – pop in and have a chat with us and find out more about what’s going on in your area.

Projects being represented:

Crystal Rig IV

Branxton Substation

Eastern Green Link 1

Berwick Bank Offshore Wind Farm

Dunbar BESS (between Thistly Cross & Pitcox)

Energy Projects Traffic and Travel Drop-in poster


Image 2 – Innerwick Old School House (What3Words – dozens.hardening.melt)

Innerwick Old School

Sign up for email updates · See previous bulletins