Berwick Bank Wind Farm – planning update

SSE Renewables have now submitted a detailed application to East Lothian Council regarding their substation. This is the 2nd of 3 applications providing further detail, following their planning permission which has been granted in principle for the onshore infrastructure.



Click on the button below for more information and a link to review and comment on the application.


If you would like to make comments to be considered by East Lammermuir Community Council in any response they make, please send to info@elcc.scot by 1st May

Beth’s Blog – Empowering Communities through the Energy Transition


As my first year in East Lammermuir fast approaches I have been reflecting on how the challenges and opportunities from the clean energy transition, being played out on the ground in this community, are at the sharp edge of a national debate…


Click the button to continue reading.

Branxton Substation enabling works





Following discussions with the local community, a Temporary Traffic Regulation Order (TTRO) has now been agreed with East Lothian Council to cover the area around the two sets of traffic lights on Bilsdean and Dunglass bridges (U220 on the map).

The TTRO is now in place and restricts vehicles for the Branxton project to 20mph, and the lights will be operating on a series of short dates throughout April and into early May. These include:



Thursday 09 April (PM)- Friday 10 April (AM)

Monday 13 April- Tuesday 14 April (AM)

Thursday 16 April  (PM)- Friday 17 April (AM)

Monday 20 April- Tuesday 21 April (AM)

Thursday 23 April  (PM)- Friday 24 April (AM)

Monday 27 April- Tuesday 28 April (AM)

Thursday 30 April  (PM)- Friday 01 May (AM)


The traffic lights in place on the C120 (see map) have been extended to accommodate additional road improvement works and will now be in place to 15th April. This delay impacts on the timing of the planned existing slip road closure, which has to wait until after the traffic lights have ended. East Lothian Council have issued a road closure notice for 30th April to 28th May for the slip road closure (details via button below). Pedestrian/cycle access will be maintained throughout.




We appreciate the community’s patience during these works and encourage people to contact the project.communications@spenergynetworks.co.uk  email address with any questions.


Image: area of impact with road numbers

Map of the roads affected by the Branxton works near Bilsdean


Path closures – A1 north side near Skateraw


SP Energy Networks’ EGL1 project have issued this notice:


To facilitate the construction of haul roads, trenching, and pipework ducting, and ensure public safety, we must temporarily restrict access to the track on the north side of the A1 near Skateraw.

Periodic closure of the track is scheduled to begin on 30 March 2026 and is expected to continue until 2028.


Click the link below for more information.



We will share times and dates of closure planned for the week ahead in this bulletin, but please note that unscheduled closures could happen a short notice.


8/4 update from the project:


14 April is the earliest date the unofficial path will be closed. It’s possible the closure will be delayed by a couple of days and we will communicate this to you if the date changes.


Image: map of impacted track

Track north of the A1 near Skateraw marked in yellow

In case you missed it…

East Lammermuir River Catchment Restoration Project

Catch up on the latest from this exciting project via the button below!


Headline news – Sustaining Dunbar are recruiting for a Catchment Restoration Development Officer, check out the role here.

Eastern Green Link 1

landfall cable works update


Prysmian, cable contractor for the EGL1 project, have notified of plans for 24hr working over the summer period. All the details are available via the button and the map indicates the areas affected.

EGL1 cable landfall works area near Thorntonloch Beach

Springfield Solar


The Scottish Government’s Planning and Environmental Appeals Division (DPEA) has written to everyone who submitted a response regarding the Public Inquiry that appears to have been decided upon, in connection with the Section 36 Electricity Act application for planning consent to the Energy Consents Unit (ECU). Please check your spam folders if you submitted a representation and haven’t seen this.


As soon as ELCC has more information regarding the Springfield Solar development it will be included in a future bulletin.

Aikengall Wind Farm traffic


There is currently an increase in traffic up to Aikengall wind farm, which potentially will last for another week, due to urgent road works, it should all be daytime traffic and no more than 20 trucks, so 40 movements in total over the period.


Image: the access road is marked in green and the wind farm shown as triangles.

Access road to Aikengall in green, with wind turbines marked by triangles



Crystal Rig IV Traffic Alerts

Click the link below for the latest information about traffic movements from Fred. Olsen Renewables.