Energy Projects Bulletin — 9 October 2025

Historical bulletin — originally published 9 October 2025

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

Logo

Energy Projects News Bulletin

Lorries in Our Lanes

Join us on Monday 10th November for updates on the current and upcoming construction of energy projects, focused on their impacts on traffic and travel.

There will be opportunity to hear your views on how disruption can be minimised for you as local residents. If you have any questions to raise in advance please reply to this email so we can make sure we have all the relevant information gathered for the evening.

Lorries in Our Lanes campaign on the East Lammermuir Developments website

The poster lists the meeting for 6.30–8 pm on Monday 10 November 2025 at Innerwick Old School House. The Community Traffic and Travel Forum hosted it to discuss construction traffic and road impacts from Eastern Green Link 1, Branxton Substation and Crystal Rig IV. The poster gives beth@elep.scot as the contact.

Crystal Rig I Repower


Fred. Olsen Renewables have submitted an energy consents application to the Scottish Government’s Energy Consents Unit for the repowering of Crystal Rig I.



Comments from local residents can be sent to East Lammermuir Community Council to include in our response, please send to info@elcc.scot by 20th October.


Notice of the application, with details of how to respond to the consultation can be found 
here.


A letter setting out how the proposal has been altered in response to community views can be viewed here.


A hard copy of the Environmental Impact Assessment Report (EIAR) is available at the Scottish Borders Council Headquarters, Bowden Road, Newtown St, Boswells TD6 0SA. An additional copy is available to view in the Outdoor Centre (Old School House) in Innerwick. Viewing is by application – see flier for details:

Traffic Alerts

Click the link below for the latest information about construction traffic movements from Fred. Olsen Renewables.

In case you missed it…

Update on road closure for EGL1

Barns Ness Terrace


Please note this road closure will now be commencing on 13 October.

The end date of 20 October remains unchanged.


Prysmian, one of the contractors for Eastern Green Link 1 (EGL1), have let us know that the upcoming closure on Barns Ness Terrace, Innerwick, has now been approved by East Lothian Council. 


The closure will affect the 253 bus service, which travels down this road.  The works take place during the school holidays, so the school bus will not be affected. Appropriate road signage will be put in place one week before the works begin.    

 

Details and exact location can be found on the Road Works Scotland website, by searching with the reference code EL109-195/25/AC (3808475). 

A cross marks the closure on Barns Ness Terrace east of Innerwick village, just west of the junction on the road towards Fouracres.

New guide to energy consents process

Planning Aid Scotland have recently published a very helpful information sheet: “Navigating the Consenting Process for Renewable Energy Developments”