Energy Projects Bulletin — 18 June 2026

Historical bulletin — originally published 18 June 2026

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

ELCC Energy Projects

Energy Projects News Bulletin



Warm Homes Project Residents’ Meeting – 30 June  

Locally-based and community-owned Lothian Heat CIC has been appointed by ELCC to deliver the Warm Homes Project.


The East Lammermuir Warm Homes Project has experienced a high volume of sign-ups since we launched last week!

We’ve decided to hold a Residents’ Information Evening on Tuesday 30th June at 7pm in Innerwick Old School – all East Lammermuir residents are invited to attend, including all tenants, homeowners and landlords in the East Lammermuir area.

Ellen will be introducing the project, including who Lothian Heat CIC are, how her role as project manager will support you, alongside the people who are supporting the project, including Chris Bruce, chair of the community council, and also Martin Hayman, the Local Heat and Energy Efficiency Strategy Officer from East Lothian Council.

We will be talking about where we are now and our current plans to move forward. This is also an opportunity for you to ask questions in a relaxed setting, speak with other residents who are interested, and tell us more about the barriers you are currently facing which we can help remove to enable your homes to be warmer, and easier to heat. This will help shape the direction of the project and guide us moving forward to ensure we deliver the best outcomes for all East Lammermuir residents.

It would be great if you could let Ellen know if you are able to attend by emailing her at ellen.abbi@lothianheat.org

Also, if you haven’t done so already, and don’t want to miss out on the opportunities the Warm Homes Project will make available, please register your interest today by filling out the 5-minute online form at East Lammermuir Warm Homes Project – Interest Form – Fill out form 

More information is available via the button below.

East Lammermuir Warm Homes Project on the Lothian Heat website

NnG Community Fund

Open for applications, deadline 2 August 2026



Funding is available for projects that support delivery of East Lammermuir’s ambitions for:

Warmer, more efficient homes

A new active travel network

Improved community transport links

Improved local biodiversity


Find out more about the fund and how to apply via the button.




Eastern Green Link 1 – cables contractor update

Path banksman – A1 north side near Skateraw



The path between A1 and Skateraw remains safely open to the public thanks to the introduction of an onsite banksman.

We always strive to keep this route accessible to the community whenever possible without compromising public safety.

  • Path status: The path was officially opened on Tuesday 16 June, and will remain open until further notice (including evenings, overnight, and weekends).

  • Onsite safety: The banksman is stationed onsite during working hours (7.00am – 7.00pm, Monday to Sunday) to safely guide vehicles and heavy machinery during intermittent path crossings.



Should any of these details change, we will let you know via the weekly bulletin.


EGL1 contact: project.communications@spenergynetworks.co.uk


Image: map of path

Path near Skateraw marked in yellow

Berwick Bank substation details being reviewed by  Planning Committee

Details of matters specified in planning condition 2 of the planning permission for the Berwick Bank onshore works (substation development area including the substation enabling works and the substation) will be reviewed at East Lothian Council’s Planning Committee meeting on Wednesday 24 June. Find out more and watch the live webcast via the button.


Image: approved substation location – orange box

Approved Berwick Bank substation location marked in orange

Crystal Rig 1 Repowering Application



A further opportunity to comment on this project has arisen.

The Scottish Government’s Energy Consent Unit have required Fred. Olsen Renewables to re-advertise and re-consult on the above application due to a submission confirming their intention to utilise the existing Crystal Rig 1 grid connection.

Fred. Olsen Renewables have issued this notice: Crystal Rig 1 Repower additional information public notice. Hard copies of the information on the grid connection are available, please contact Cris Thacker to arrange to view: Cris.Thacker@fredolsen.com

Comments may be submitted via www.energyconsents.scot, using the ECU reference number (ECU00005089) by 13th July.

Image: CR1 (dark blue dots – constructed) and CR1 repower (turquoise dots- in planning), turquoise lines indicate the planning boundary including the construction route for the site.

Explore the East Lammermuir energy developments map

Construction vehicle signage

The Community Traffic and Travel Forum’s proposal for energy projects for vehicle signage has now been adopted for all SP Energy Networks projects. We hope this will make it easier for community members to identify which project construction vehicles are associated with, and make reporting of any issues more streamlined.


Find out more via the button

SP Energy Networks Branxton Substation vehicle side sign

Branxton Substation enabling works






To complete the new A1 slip road the temporary traffic barrier must be removed to tie in the new road. This requires night shift working from 16th to 18th June. Works will be completed as quickly as possible, and steps will be taken to minimise noise.



Forthcoming works include progressing the 3km haul road to the Branxton substation site, which crosses public roads at three locations.  To support construction of these junctions (including signage, road widening and resurfacing), road closures have been agreed with East Lothian Council as follows:  

  • Location 2: Lawfield Road – 11th June to 5th July

  • Location 3: ZU215 – 4th to 27th August

  • Location 4:C121 – 19th August to 13th September

  • C121 road widening requires a closure at Location 5: 14th September to 12th October


As construction on the project continues, we will continue to carefully phase activities to minimise disruption and work closely with the community – ensuring residents are kept informed. 




SPEN appreciate the community’s patience during these works and encourage people to contact the stakeholder engagement team on 07345 482038 or email project.communications@spenergynetworks.co.uk

with any questions.


For the latest update click the button below


Image: locations of upcoming road closures (location 1, existing A1 slip road – now reopened)

Aerial view of the Branxton works area and nearby roads

Berwick Bank Windfarm

Variation application (offshore element of project)

Last day!


Berwick Bank Wind Farm Limited have submitted an application to the Scottish Ministers for a variation to the existing section 36 consent granted on 31 July 2025. The application documents are available for review and comments can be sent to MD.MarineRenewables@gov.scot by 18 June 2026


The variation request is to:

  • Allow for the discharge of conditions for each proposed phase of the Development of the Berwick Bank Wind Farm, as opposed to the development as a whole and;

  • To correct discrepancies in the co-ordinates included in the offshore transmission infrastructure (part 1) and offshore transmission infrastructure (part 2) marine licences.

The section 36 consent and marine licence variation applications, and supporting documentation can be accessed via the link in the button.

EGL1 coastal works near Thorntonloch Beach


Starting 6 June through 29 July, works relating to casing installation and fusion welding will commence near the Torness shoreline. To ensure the project remains on schedule, these works will operate 24 hours a day, 7 days a week. Dates are subject to change.

 

  • Daytime: Focus on casing installation along the cable route.

  • Nighttime: Welding activities, including work under the railway crossing.

 

Prysmian (cable contractor) for the Eastern Green Link 1 (EGL1) project is committed to minimising disruption. Noise levels will remain below 96 dB(A), comparable to a lawnmower, and silenced generators will be utilised at night. To ensure safety and visibility, 20 light towers will be active; however, these will be directed inward to prevent glare on the railway and highway.

In case you missed it…

Energy Projects Partnership Newsletter

Check out our quarterly partnership newsletter via button, hard copies available on request from beth@elep.scot

Public Inquiry into the Springfield Solar Farm & Battery Energy Storage System



This proposed project will be going to Public Legal Inquiry and ELCC intend to take part in this process. Voltalia have been asked by the Reporter at the Scottish Government’s Planning and Environmental Appeals Division (DPEA) to provide further information on the following points:

  • their Environmental Impact Assessment must include the grid connection (as per Raeshaw Farms judgement)

  • transport and access

  • landscape and visual impact

  • acoustic barriers


Map: proposed site indicated in pink

Springfield Solar Farm proposal area marked in pink

Highlands & Islands Green Energy Conference 2026


ELCC Chair, Chris Bruce took part in a panel discussion “Gaining Community Buy-in & Associated Challenges” today at a green energy conference in Inverness sharing experiences from East Lammermuir, and SE Scotland.

Also taking part were GB Energy, Fred. Olsen Renewables and Skills Development Scotland. There were discussions about workforce and the next generation, community benefits and community engagement. We look forward to hearing Chris’s reflections at the next community council meeting.

Panel at the Highlands and Islands Green Energy Conference


EGL1 Park and Ride

A planning application has been by East Lothian Council for a temporary park-and-ride facility off Spott Road, Dunbar for construction workers for the Eastern Green Link 1 (EGL1) convertor station site at Oxwellmains. The park and ride site is located on vacant development land within Dunbar Business Park.

Find out more via the button.

Overnight Resurfacing at A1 South of Innerwick Junction

BEAR Scotland, on behalf of Transport Scotland will be undertaking essential overnight carriageway resurfacing on the A1 in both directions, south of Innerwick Junction over 19 nights from Monday 8th June to Thursday 2nd July, from 19:30 to 06:00 each night. No works are currently planned for Saturday or Sunday nights.

Traffic restrictions: The A1 will remain open, however a 10mph convoy traffic management setup will be in place in both directions. The A1 southbound dual carriageway will be restricted to a single lane on approach to the site during the works.


Road users looking to head South on the A1 from the Innerwick Junction are to follow the A1 Northbound to Spott Roundabout and return on the A1 Southbound (blue route).

Map of overnight resurfacing south of Innerwick Junction


Crystal Rig IV

Click the link below for the latest information  from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins