Energy Projects News Bulletin |
|
|
Reporting Portal NOW LIVE! |
|
|
|
Now live on the East Lammermuir Developments website, the Reporting Portal is a streamlined way for community members to report issues with the construction of the energy developments.
Using a simple form, the nature of the issue and any details you can provide to help with follow up can be submitted along with optional photos and the location.
Reports are received by project contacts and Beth Landon, Energy Projects Partnership Manager, and you will receive follow up from the relevant person.
Please let us know how you find using it and any suggestions to make it better by emailing beth@elep.scot |
|
|
|
|
Warm Homes Project A message from Project Manager, Ellen Abbi – A big thank you to all of you who joined us at the Warm Homes Project Information Evening on Tuesday! It was wonderful to see so much interest in the project at its launch event, and get a chance to get your thoughts directly which will help us move forward. My thanks also goes to Chris Bruce, ELCC Chair, for introducing the project, and Martin Hayman, Local Heat and Energy Efficiency Strategy Officer at East Lothian Council, for his informative presentation on current proposals for heating solutions in East Lammermuir, and for bringing along a Heat Interface Unit! It was also wonderful to have Matthew and George, Citizens Advice Bureau Energy Advisors attending with their offer of a free home energy visit. I will be sending out an update and the presentation materials shortly to those who have registered interest. If you would also like to receive a copy directly, and haven’t done so already, please register your interest in the project using the ‘Register your Interest’ Form, via the Button below, or email Ellen at ellen.abbi@lothianheat.org.
Image 2 – Ellen Abbi and Martin Hayman (Local Heat and Energy Efficiency Officer, East Lothian Council) at Innerwick meeting 30th June More information is available via the button below. |
|
|
|
|
|
|
Dispatches from the Grid FrontlineEast Lammermuir features in a podcast! Local Storytelling Exchange’s Clare Harris shares insights from a series of deep delves in communities along the East coast of the UK most impacted by the great grid upgrade.
Check it out via the button below and view the interactive report via the 2nd button. |
|
|
|
|
|
Morvern Offshore Wind FarmApplications have been submitted to the Scottish Government Marine Directorate for the Morven North and South offshore wind farm projects, off the Aberdeenshire Coast.
These applications do not include the transmission infrastructure to bring the power onshore. The connections for the wind farm are determined by National System Operator (NESO), one of which is expected to be in the Branxton area. The developers do not yet have their grid connection agreement, which will provide details of timing and location. They have been advised that the details of this agreement will be provided towards the end of this year.
We will keep the community updated as we learn more. In the meantime the application documents for the offshore elements of the project can be found via the first button. Information about where to view hard copies is in the East Lothian Courier notice below.
Please note the deadline for comment is 16 July 2026, to be sent to MD.MarineRenewables@gov.scot |
|
|
|
|
|
EGL1 Closure of Barns Ness Terrace, Innerwick and Deliveries Bilsdean/Dunglass
Road closure Innerwick: Closure of Barns Ness Terrace, Innerwick, 2nd-13th July. This is to allow for surfacing works.
Deliveries via Dunglass traffic route w/c 29 June
Prysmian (cable contractor) for the Eastern Green Link 1 (EGL1) are having a quantity of portacabins delivered to the Bilsdean compound via the road going past Dunglass from w/c 29th June: Approximately 25 vehicle movements are scheduled between Monday 29 June-Friday 3 July, between the hours of 7am-7pm. No traffic management or diversions will be required.
|
|
|
|
|
|
|
EGL1 coastal works near Thorntonloch Beach
Starting 6 June through 29 July, works relating to casing installation and fusion welding will commence near the Torness shoreline. To ensure the project remains on schedule, these works will operate 24 hours a day, 7 days a week. Dates are subject to change. Daytime: Focus on casing installation along the cable route. Nighttime: Welding activities, including work under the railway crossing.
Update June 26th – “Much of the activity is not yet visible from the beach itself. The main work is taking place within the secure compound we have built close to the railway and highway, rather than directly on the beach. Our schedule has adjusted slightly as we finalised our final preparatory and administrative stages, which moved our original start date back. However, mobilisation works for the casing, just west of the railway line, successfully began this week. The landfall works, which will require 24/7 operations once underway, are scheduled to start in the next few weeks. We currently expect these to wrap up in early September. You will notice a lot more visible activity in the area very soon. Please note that these dates remain subject to change depending on progress, but we will keep the community updated.”
Prysmian (cable contractor) for the Eastern Green Link 1 (EGL1) project is committed to minimising disruption. Noise levels will remain below 96 dB(A), comparable to a lawnmower, and silenced generators will be utilised at night. To ensure safety and visibility, 20 light towers will be active; however, these will be directed inward to prevent glare on the railway and highway. |
|
|
|
Branxton Substation enabling works
Upcoming works include progressing the 3km haul road to the Branxton substation site, which crosses public roads at three locations. To support construction of these junctions (including signage, road widening and resurfacing), road closures have been agreed with East Lothian Council as follows: Location 2: Lawfield Road – 11th June to 5th July Location 3: ZU215 – 4th to 27th August Location 4:C121 – 19th August to 13th September C121 road widening requires a closure at Location 5: 14th September to 12th October
As construction on the project continues, we will continue to carefully phase activities to minimise disruption and work closely with the community – ensuring residents are kept informed.
SPEN appreciate the community’s patience during these works and encourage people to contact the stakeholder engagement team on 07345 482038 or email project.communications@spenergynetworks.co.uk with any questions.
For the latest update click the button below
Image: locations of upcoming road closures (location 1, existing A1 slip road – now reopened) |
|
|
|
|
|
Overnight Resurfacing at A1 South of Innerwick Junction finished earlyBEAR Scotland, on behalf of Transport Scotland has been undertaking essential overnight carriageway resurfacing on the A1 in both directions, south of Innerwick Junction over 19 nights from Monday 8th June – 2nd July. Update 2nd July – Tonight’s shift will not be required as the works have been completed ahead of schedule. |
|
|
|
|
Energy Projects Partnership NewsletterCheck out our quarterly partnership newsletter via button, hard copies available on request from beth@elep.scot or can be found in Stenton and Spott village halls, Innerwick Old School House |
|
|
|
|
|
Biodiversity News Welcome to Jenny Gries |
|
|
|
Hello! My name is Jenny Gries, and I’m delighted to have joined Sustaining Dunbar as Development Officer for the Catchment Restoration Project along the Spott and Dry burns. Since starting at the end of May, I’ve been enjoying learning about and supporting the survey work carried out by our partners at Forth Rivers Trust, and I’ve also had the pleasure of meeting a number of local landowners who are interested in the project. Having lived in East Lothian for nearly 15 years, it has been fascinating to get to know the variety and beauty of the East Lammermuir landscape — a real mosaic of farmland, woodland, moorland and infrastructure. I’m excited to be involved in a project that sits at this complex intersection of people and place, and that puts communities at the heart of creating healthier, more connected and resilient landscapes. I’m looking forward to meeting many more community members and landowners over the coming months. If you own land along either of the burns, or live locally and would like to hear more about the project, please get in touch: mapping@sustainingdunbar.org |
|
|
|
|
NnG Community FundOpen for applications, deadline 2 August 2026
Funding is available for projects that support delivery of East Lammermuir’s ambitions for: Warmer, more efficient homes A new active travel network Improved community transport links Improved local biodiversity
Find out more about the fund and how to apply via the button. |
|
|
|
|
|
Construction vehicle signageThe Community Traffic and Travel Forum’s proposal for energy projects for vehicle signage has now been adopted for all SP Energy Networks projects. We hope this will make it easier for community members to identify which project construction vehicles are associated with, and make reporting of any issues more streamlined.
Find out more via the button |
|
|
|
|
|
Crystal Rig 1 Repowering Application
A further opportunity to comment on this project has arisen. The Scottish Government’s Energy Consent Unit have required Fred. Olsen Renewables to re-advertise and re-consult on the above application due to a submission confirming their intention to utilise the existing Crystal Rig 1 grid connection. Fred. Olsen Renewables have issued this notice: Crystal Rig 1 Repower additional information public notice. Hard copies of the information on the grid connection are available, please contact Cris Thacker to arrange to view: Cris.Thacker@fredolsen.com Comments may be submitted via www.energyconsents.scot, using the ECU reference number (ECU00005089) by 13th July. Image: CR1 (dark blue dots – constructed) and CR1 repower (turquoise dots- in planning), turquoise lines indicate the planning boundary including the construction route for the site. |
|
|
|
|
|
Crystal Rig IV Click the link below for the latest information from Fred. Olsen Renewables. |
|
|
|
|
|
|