ELCC Energy Projects

Energy Projects News Bulletin

Morvern Offshore Wind Farm

Applications have been submitted to the Scottish Government Marine Directorate for the Morven North and South offshore wind farm projects, off the Aberdeenshire Coast.


These applications do not include the transmission infrastructure to bring the power onshore. The connections for the wind farm are determined by National System Operator (NESO), one of which is expected to be in the Branxton area. The developers do not yet have their grid connection agreement, which will provide details of timing and location. They have been advised that the details of this agreement will be provided towards the end of this year.


We will keep the community updated as we learn more. In the meantime the application documents for the offshore elements of the project can be found via the first button. Information about where to view hard copies is in the East Lothian Courier notice below.


Please note the deadline for comment is 16 July 2026, to be sent to MD.MarineRenewables@gov.scot

Biodiversity News

Welcome to Jenny Gries

Jenny Gries, Catchment Restoration Project development officer


Hello! My name is Jenny Gries, and I’m delighted to have joined Sustaining Dunbar as Development Officer for the Catchment Restoration Project along the Spott and Dry burns.

Since starting at the end of May, I’ve been enjoying learning about and supporting the survey work carried out by our partners at Forth Rivers Trust, and I’ve also had the pleasure of meeting a number of local landowners who are interested in the project.

Having lived in East Lothian for nearly 15 years, it has been fascinating to get to know the variety and beauty of the East Lammermuir landscape — a real mosaic of farmland, woodland, moorland and infrastructure. I’m excited to be involved in a project that sits at this complex intersection of people and place, and that puts communities at the heart of creating healthier, more connected and resilient landscapes.

I’m looking forward to meeting many more community members and landowners over the coming months. If you own land along either of the burns, or live locally and would like to hear more about the project, please get in touch: mapping@sustainingdunbar.org

Summit to Sea project updates and events



Warm Homes Project Residents’ Meeting – 30 June

Next Tuesday

Locally-based and community-owned Lothian Heat CIC has been appointed by ELCC to deliver the Warm Homes Project.


The East Lammermuir Warm Homes Project has experienced a high volume of sign-ups since we launched two weeks ago.

We’ve decided to hold a Residents’ Information Evening on Tuesday 30th June at 7pm in Innerwick Old School – all East Lammermuir residents are invited to attend, including all tenants, homeowners and landlords in the East Lammermuir area.

Ellen will be introducing the project, including who Lothian Heat CIC are, how her role as project manager will support you, alongside the people who are supporting the project, including Chris Bruce, chair of the community council, and also Martin Hayman, the Local Heat and Energy Efficiency Strategy Officer from East Lothian Council.

We will be talking about where we are now and our current plans to move forward. This is also an opportunity for you to ask questions in a relaxed setting, speak with other residents who are interested, and tell us more about the barriers you are currently facing which we can help remove to enable your homes to be warmer, and easier to heat. This will help shape the direction of the project and guide us moving forward to ensure we deliver the best outcomes for all East Lammermuir residents.

It would be great if you could let Ellen know if you are able to attend by emailing her at ellen.abbi@lothianheat.org

Also, if you haven’t done so already, and don’t want to miss out on the opportunities the Warm Homes Project will make available, please register your interest today by filling out the 5-minute online form at East Lammermuir Warm Homes Project – Interest Form – Fill out form 

More information is available via the button below.

East Lammermuir Warm Homes Project on the Lothian Heat website

EGL1 Deliveries Bilsdean/Dunglass and closure of Barns Ness Terrace, Innerwick



Deliveries via Dunglass traffic route w/c 29 June 



Prysmian (cable contractor) for the Eastern Green Link 1 (EGL1) are having a quantity of portacabins delivered to the Bilsdean compound via the road going past Dunglass from w/c 29th June:

 

Approximately 25 vehicle movements are scheduled between Monday 29 June-Friday 3 July, between the hours of 7am-7pm.  No traffic management or diversions will be required.


Road closure Innerwick:

Closure of Barns Ness Terrace, Innerwick, 2nd-13th July. This is to allow for surfacing works.

Barns Ness Terrace road closure map
Road on the delivery route

Construction vehicle signage

The Community Traffic and Travel Forum’s proposal for energy projects for vehicle signage has now been adopted for all SP Energy Networks projects. We hope this will make it easier for community members to identify which project construction vehicles are associated with, and make reporting of any issues more streamlined.


Find out more via the button

EGL1 and Branxton construction vehicle identification signs

Branxton Substation enabling works







Upcoming works include progressing the 3km haul road to the Branxton substation site, which crosses public roads at three locations.  To support construction of these junctions (including signage, road widening and resurfacing), road closures have been agreed with East Lothian Council as follows:  

  • Location 2: Lawfield Road – 11th June to 5th July

  • Location 3: ZU215 – 4th to 27th August

  • Location 4:C121 – 19th August to 13th September

  • C121 road widening requires a closure at Location 5: 14th September to 12th October


As construction on the project continues, we will continue to carefully phase activities to minimise disruption and work closely with the community – ensuring residents are kept informed. 




SPEN appreciate the community’s patience during these works and encourage people to contact the stakeholder engagement team on 07345 482038 or email project.communications@spenergynetworks.co.uk

with any questions.


For the latest update click the button below


Image: locations of upcoming road closures (location 1, existing A1 slip road – now reopened)

Aerial view of the Branxton road closure locations

EGL1 coastal works near Thorntonloch Beach


Starting 6 June through 29 July, works relating to casing installation and fusion welding will commence near the Torness shoreline. To ensure the project remains on schedule, these works will operate 24 hours a day, 7 days a week. Dates are subject to change.

 

  • Daytime: Focus on casing installation along the cable route.

  • Nighttime: Welding activities, including work under the railway crossing.

 

Prysmian (cable contractor) for the Eastern Green Link 1 (EGL1) project is committed to minimising disruption. Noise levels will remain below 96 dB(A), comparable to a lawnmower, and silenced generators will be utilised at night. To ensure safety and visibility, 20 light towers will be active; however, these will be directed inward to prevent glare on the railway and highway.

In case you missed it…

Energy Projects Partnership Newsletter

Check out our quarterly partnership newsletter via button, hard copies available on request from beth@elep.scot or can be found in Stenton and Spott village halls, Innerwick Old School House

NnG Community Fund

Open for applications, deadline 2 August 2026



Funding is available for projects that support delivery of East Lammermuir’s ambitions for:

Warmer, more efficient homes

A new active travel network

Improved community transport links

Improved local biodiversity


Find out more about the fund and how to apply via the button.

Overnight Resurfacing at A1 South of Innerwick Junction

BEAR Scotland, on behalf of Transport Scotland will be undertaking essential overnight carriageway resurfacing on the A1 in both directions, south of Innerwick Junction over 19 nights from Monday 8th June to Thursday 2nd July, from 19:30 to 06:00 each night. No works are currently planned for Saturday or Sunday nights.

Traffic restrictions: The A1 will remain open, however a 10mph convoy traffic management setup will be in place in both directions. The A1 southbound dual carriageway will be restricted to a single lane on approach to the site during the works.


Road users looking to head South on the A1 from the Innerwick Junction are to follow the A1 Northbound to Spott Roundabout and return on the A1 Southbound (blue route).

A1 diversion via Spott Roundabout

Crystal Rig 1 Repowering Application



A further opportunity to comment on this project has arisen.

The Scottish Government’s Energy Consent Unit have required Fred. Olsen Renewables to re-advertise and re-consult on the above application due to a submission confirming their intention to utilise the existing Crystal Rig 1 grid connection.

Fred. Olsen Renewables have issued this notice: Crystal Rig 1 Repower additional information public notice. Hard copies of the information on the grid connection are available, please contact Cris Thacker to arrange to view: Cris.Thacker@fredolsen.com

Comments may be submitted via www.energyconsents.scot, using the ECU reference number (ECU00005089) by 13th July.

Image: CR1 (dark blue dots – constructed) and CR1 repower (turquoise dots- in planning), turquoise lines indicate the planning boundary including the construction route for the site.

Explore the Crystal Rig repowering boundary on the interactive developments map




Eastern Green Link 1 – cables contractor update

Path banksman – A1 north side near Skateraw



The path between A1 and Skateraw remains safely open to the public thanks to the introduction of an onsite banksman.

We always strive to keep this route accessible to the community whenever possible without compromising public safety.

  • Path status: The path was officially opened on Tuesday 16 June, and will remain open until further notice (including evenings, overnight, and weekends).

  • Onsite safety: The banksman is stationed onsite during working hours (7.00am – 7.00pm, Monday to Sunday) to safely guide vehicles and heavy machinery during intermittent path crossings.



Should any of these details change, we will let you know via the weekly bulletin.


EGL1 contact: project.communications@spenergynetworks.co.uk


Image: map of path

Path near Skateraw marked in yellow


Crystal Rig IV

Click the link below for the latest information  from Fred. Olsen Renewables.

Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.