Energy Projects Bulletin — 6 November 2025

Historical bulletin — originally published 6 November 2025

This bulletin is retained for reference. Events, application deadlines and other opportunities mentioned may have passed. For current information, see our latest news and funding pages (opens in a new tab).

← All Energy Projects bulletins

Logo

Energy Projects News Bulletin

EGL1 update – Dunglass traffic management

The roadworks symbol marks the Bilsdean Road crossing of Dunglass Burn, south of the A1 and just north of Killflat Wood.

The Eastern Green Link 1 team have notified us about a temporary traffic lights system being put in place from 10-21 November in the Dunglass area to allow for HGV movements. Click the link below for further details.

Lorries in Our Lanes campaign on the East Lammermuir Developments website

The poster lists the meeting for 6.30–8 pm on Monday 10 November 2025 at Innerwick Old School House. The Community Traffic and Travel Forum hosted it to discuss construction traffic and road impacts from Eastern Green Link 1, Branxton Substation and Crystal Rig IV. The poster gives beth@elep.scot as the contact.

Join us on Monday 10th November for updates on the current and upcoming construction of energy projects, focused on their impacts on traffic and travel.

There will be opportunity to hear your views on how disruption can be minimised for you as local residents. If you have any questions to raise in advance please reply to this email so we can make sure we have all the relevant information gathered for the evening.

Springfield Solar Farm

East Lothian Council Planning Committee reviewed the Planning Officer report for this application from Voltalia at their meeting on Tuesday 4th November. East Lothian Council are a statutory consultee, but do not have the final decision on consenting this proposal.


Council unanimously voted to object to this proposal, which is to be determined by Scottish Government Energy Consents Unit.

Crystal Rig I Repower

It’s not too late to have you say!


Comments can be sent to East Lothian Council who are a consultee in the process (deadline: Friday 28th November) via environment@eastlothian.gov.uk



The application

Fred. Olsen Renewables have submitted an energy consents application to the Scottish Government’s Energy Consents Unit for the repowering of Crystal Rig I.



Notice of the application, with details of how to respond to the consultation can be found here.


A letter setting out how the proposal has been altered in response to community views can be viewed here.


A hard copy of the Environmental Impact Assessment Report (EIAR) is available at the Scottish Borders Council Headquarters, Bowden Road, Newtown St, Boswells TD6 0SA. An additional copy is available to view in the Outdoor Centre (Old School House) in Innerwick. Viewing is by application – see flier for details:

Our very first newsletter was posted to residents last week, check it out here!

Energy Projects Partnership

key priorities

The diagram groups the partnership’s priorities into five areas.

  • Community-led development. Align the community benefit strategy with the four Local Place Plan priorities, build community capacity and engagement, and link biodiversity net gain to the community-led plan.
  • Construction impacts. Work through the traffic and biodiversity groups, develop construction traffic proposals such as combined signage, and monitor the discharge of planning conditions.
  • Partnership working. Establish an advisory group, hold Energy Developments meetings, build on the steering group’s strengths and provide a partnership budget.
  • Communication. Reach more people through email bulletins, a reporting portal, a newsletter, a single point of contact and the Energy Developments website.
  • Sharing learning. Share lessons locally first, then between communities nationally, and contribute to energy strategy planning.

At the Energy Developments meeting in September, participants were asked for their thoughts on the partnership:


  • What has been working well?

  • What could we do differently?

  • What next?



The feedback has been analysed and formed into a set of priorities for the Energy Projects Partnership for the next 18 months.


Check out the meeting summary for more details plus an overview of the presentations given at the meeting.


Traffic Alerts

Click the link below for the latest information about construction traffic movements from Fred. Olsen Renewables.

In case you missed it…

Crystal Rig IV update

Fred. Olsen Renewables have let us know that they only have one more abnormal load delivery with police escort for the Crystal Rig IV site (via the Innerwick junction of the A1) and it will be a blade delivery. This has been delayed at port and they don’t have a date for this final delivery, but once they know they will communicate it via their construction traffic updates in these bulletins (see below) and the via text alert system.



Once the final abnormal load is delivered, they will provide an update to the community in terms of when they will complete the project.

Sign up for email updates · See previous bulletins

Stay informed

Receive a weekly bulletin from East Lammermuir Energy Partnership.