Planning and community records

Historical material from the former ELCC website. These records describe the position at the time. Events, advice, contacts and funding information may no longer apply. For current information, visit the Community Council page.

Back to historical records and documents

Choose a record below to read its original text. Dates shown are original publication dates.

East Lothian Infrastructure Projects — 2023-07-13

Plans are already under way for the Berwick Bank Wind Farm, Branxton Battery Energy Storage, North Belton Battery Energy Storage, Crystal Rig IV onshore Windfarm, Crystal Rig solar farm, Capping off and restoration of Oxwellmains Landfill and the Eastern Link project, as well as the decommissioning of Torness Power Station.

Each of the projects is expected to bring hundreds of workers to the area, but concerns have been expressed about where they will stay, additional traffic on the road and ensuring that the area reaps the benefits.

Innerwick and its surrounding villages and hamlets are on the frontline, being on the main route taken by the cables and construction traffic. Stenton and Spott are impacted to a lesser extent by the development at North Belton.

Berwick Bank Wind Farm, which has already secured a grid connection at Branxton, near Torness, will be created 40 kilometres off the county coast and feature more than 200 turbines, the largest windfarm in Europe and possibly the world.

Braxton and Belton Battery Storage facilities are to help match energy demand at peaks with the wind generation available by storing energy at peak generation and releasing it at peak demand.

Fred Olsen Renewables will be adding a further 11 turbines and a Solar Farm at their Crystal Rig site up in the Lammermuir hills

The Eastern Link project involves more than £1.5 billion of underwater cabling linking Thorntonloch Beach, near the East Lothian town, to County Durham. This will form part of the backbone of the UK’s energy supply.

Finally, Torness Power Station is expected to stop generating power in March 2028. De-fuelling and decommissioning is expected to last for around 20 years

Boundaries of the main projects – darker shades show overlapping areas

Neart na Gaoithe (NnG) offshore wind farm

The Neart na Gaoithe (NnG) offshore wind farm will be located 15.5 km off the Fife coast and covers an area of approximately 105 km2. EDF Renewables UK acquired the project in May 2018 as part of a competitive bidding process. Completing is expected Q1 2024 more …

Braxton Energy Bank Planning Boundary

The 4 month consultation period for ELC to submit comments to ECU ends 6th August 2023. No advertised date for ECU determination but expected to be 2024. Grid connection is late 2027 so Construction, ECU Consent depending, could start early 2027 but not likely to be before this due to fixed grid connection date.

Eastern Link Planning Boundary

Braxton Substation: Planning Permission in Principle (PPP) application submitted to ELC in June 2023. Application not yet validated by ELC

Converter Station at Oxwell Mains Landfill: Planning Permission in Principle (PPP) granted by ELC in May 2023. Marine licence also granted by Scot Gov for marine cables.

Berwick Bank Planning Boundary

Application for Planning Permission in Principle (PPP) submitted April 2023, deadline for Representations closed May 23. No date for anticipated Determination Date advertised by ELC

Crystal Rig Phase IV and Solar

Crystal Rig Phase IV:
11 turbines up to 200m, 42MW
Construction commences Q3 2023
Route to site will be A1 to Innerwick Junction then south to site entrance
Crystal Rig Solar:
30MW solar array
Public consultation ongoing

Dunbar Battery Energy Storage System at North Belton

FRV TH Powertek are building a 49.9MW Battery Energy Storage System (BESS) is proposed, 850m north of Pitcox and 3km south west of Dunbar.
Underground cable to the point of connection (substation immediately south of the site).

Torness is due to end generation in March 2028.

Defueling begins when a station stops generating in 2028. EDF will remove all spent fuel from the site using the same methods used during generation. Defueling is expected to last for approximately four years, followed by a further 12 years decommissioning. The site will be cleared sometime after 2044.

Project Plan Tracker

Project Timeline

Compulsory Purchase Order Plots for Berwick Bank Wind Farms

Contact Details:

Contact us for more information and to be added to the distribution list for news updates.

email East Lothian Winds of Change

facebook https://www.facebook.com (external link — opens in a new tab)

Developer Contacts:

Regulatory & Government Contacts:

Energy Consents Unit (ECU)
Econsents_Admin@gov.scotThis is the division of Scottish Government that deal with developments covered by the Electricity Act 1989. Applications under Section 36 of this Act go directly to ECU & are determined by the ECU, albeit via consultation with the relevant local authority. 
jayne.anderson@gov.scotCase Officer for DPEA.
Appointed Reporter is Paul Cackette.
East Lothian Council (ELC)
dproudfoot@eastlothian.gov.ukDouglas Proudfoot, ELC Executive Director of Place (aka head of planning).
kdingwall@eastlothian.gov.uk Keith Dingwall, ELC Planning Service Manager. 
Elected Representatives –
MPs & MSPs
kenny.macaskill.mp@parliament.ukKenny Macaskill, MP for East Lothian, Alba Party
paul.mclennan.msp@parliament.scotPaul MacLennan, MSP East Lothian & SNP Housing Minister.
Martin.Whitfield.msp@parliament.scotMartin Whitfield List MSP for South Scotland.
Local Councillors:
ljardine1@eastlothian.gov.ukLyn Jardine, Dunbar & East Linton Ward SNP. 
Planning Submissions — 2023-05-10

East Lammermuir Community Council does its best to understand local people’s views on each planning application made for East Lammermuir. We make planning submissions on this basis.

You can see our submissions in relation to the various renewables energy infrastructure proposals here:

Comment on Newlands Hill Energy Hub (Belltown Power)

Comments on the planning application for Branxton substation 23/00616/PM

Branxton Battery Energy Storage System (submitted to Energy Consents Unit)

Energy Consents Unit  (external link — opens in a new tab)

Berwick Bank Windfarm – onshore works (submitted to East Lothian Council)

East Lothian Council planning portal (external link — opens in a new tab)

Infrastructure event — 2023-04-27

East Lammermuir Community Council
Infrastructure event 25 April 2023
Innerwick Village Hall

Planning Objections

Purpose

•To describe the range of work proposed over the coming decade, with an eye to the impact on local people

•To consider and commence appropriate liaison arrangements so that local people can plan ahead and feedback on their experience whilst the work is being done, in order to minimise negative impacts

•To hear ideas for additional legacy projects which could be put in place whilst the (electricity-related) work is done

Download the presentation here:

Please give us your thoughts and feedback, click here to fill out the feedback form: (external link — opens in a new tab)

Contacts List:

DevelopmentCompanyContact details
Eastern Link / Oxwellmains Converter station / Branxton sub-stationSPENeasternlink@spenergynetworks.co.uk
Berwick Bank Landfall / Skateraw Converter StationSSEGary Donlin gary.donlin@sse.com
Neart na Gaoithe windfarmNnGinfo@nngoffshorewind.com  
Crystal Rig IV & Solar FarmFred Olsen RenewablesKirsty Leiper kirsty.leiper@fredolsen.com www.crystalrigwindfarm.co.uk (external link — opens in a new tab)
Branxton Energy  Storage FacilityEast Coast Grid Services Ltd.  Steve Ruggi
steve.ruggi@gridcodepower.com   http://branxtonenergystorage.com/ (external link — opens in a new tab)
Dunbar Battery Energy Storage SystemSirius Planning representing FRV PowertekDan Elvin dan.elvin@thesiriusgroup.com
Decommissioning of TornessEDFAshleigh.dickson@edf-energy.com
Newlands Hill Wind Energy HubBelltown PowerMatt Olley matt.olley@belltownpower.com Sam McMillan sam.mcmillan@mcmillan.scot https://www.newlandshillwindenergyhub.com/ (external link — opens in a new tab)
Oxwellmains LandfillValenciabe confirmed
Table of Developer Contact Details
Crystal Rig 4 given consent by Scottish Government — 2021-07-09

May 2021

Crystal Rig 4, comprising 11 turbines has been given been given the go-ahead, despite objections, after Scottish Ministers agreed it would take an impact of “overwhelming importance” to stop them. The new turbines in the Lammermuir Hills sparked concern after they included plans to put red aviation lights at the top.It was argued they would be as visible as the giant cranes at the St James Centre in Edinburgh city centre were across the county and likened the towering turbines to “the towers of the new Queensferry crossing. However, in a report approved by Scottish Ministers following an appeal by windfarm operators Fred. Olsen Renewables, their Reporters ruled none of the objections were strong enough to support refusing planning permission for the turbines. The proposed development will comprise: 11 turbines 4 at up to 149.9 m tip height. 3 at up to 174.5 m tip height. 4 at up to 200 m tip height.
Eastern HVDC Link — 2021-04-06

The Eastern HVDC Link project is a proposal to install a sub-sea high-voltage direct current (HVDC) cable from Sandford Bay, at Peterhead, to Drax in England.

There are currently proposals for two Eastern HVDC Links. The link between Peterhead and Drax will be jointly developed by SSEN Transmission and National Grid. The second Eastern HVDC Link will run from Torness to Hawthorn Pit and will be jointly developed by Scottish Power Energy Networks and National Grid.

There is currently a large amount of forecasted generation that will require connection to the electricity network in the coming years and as such several upgrades are being proposed to the transmission network across the north of Scotland to facilitate this. The Eastern HVDC Link will play a key role in helping achieve Scotland’s Net-Zero targets.

An online public consultation by SP Energy Networks is scheduled for May 2021.

Polymer Recycling Facility — 2020-10-20
Valencia Waste Management Limited (formerly Viridor Waste Management) create a plastics recycling facility (PRF) beside the Dunbar Energy Recovery Facility (ERF), which opened at Oxwellmains. Early plans were submitted to East Lothian Council in February 2020, followed by a virtual public exhibition in April. Planning permission would allow Viridor to build a PRF, which would return about 85,000 tonnes per year of plastics to be re-manufactured. The proposed facility would receive “low-carbon heat and power” generated from the adjacent ERF plant and be made up of four main parts: plastics washing, plastics feed stock store, process building, and waste treatment and heat exchanger building.

Update October 2020

Proposals for the site have changed since the initial consultation in spring 2020, based on the feedback Viridor received from the local community. Concerns were expressed regarding the size of the facility and visibility of the vent, used to eliminate odour. As a result Viridor have revised proposals to limit the need for washing plastics on-site. Receiving plastics at the site, pre-washed, has allowed the removal of the vent that was part of the original proposal, whilst also ensuring no odour will be emitted from the facility. For further information please click to read the Revised proposed Polymers Recycling Facility Newsletter
Berwick Bank and Marr Bank Offshore Wind Farms — 2020-09-24

Located in the North Sea, in the outer Firth of Forth, Berwick Bank and Marr Bank offshore wind developments have the potential to deliver around 3.2GW of installed capacity, making them Scotland’s largest offshore wind farms.

Formerly known as Seagreen 2&3, Berwick Bank wind farm and Marr Bank wind farm are two distinct projects in the early stages of development, both being taken forward by SSE Renewables. The proposals are located next to one another and are over 40km off the coast of East Lothian. The consented Seagreen 1 offshore wind farm, which is in the early stages of construction and can be visited here (external link — opens in a new tab), is a separate sister project and is located to the north of Berwick Bank wind farm and Marr Bank wind farm, 27km off the coast of Angus.

Berwick Bank wind farm and Marr Bank wind farm could bring a wealth of opportunity for businesses of all sizes across a wide range of disciplines and SSE Renewables are aiming to utilise as many local, Scottish and UK based suppliers where possible throughout all stages of development and operation.

SSE Renewables and SSE Transmission have teamed up with STEM Returners to develop a programme designed to support those who’ve taken a career break or are looking to return to the sector. If you have STEM skills and want to restart your career after a break, our STEM returners programme (external link — opens in a new tab) could be for you.

Further information:

Berwick Bank Scoping Report

Presentation to ELCC August 2020

If you have any questions about this project email berwickandmarr.enquiries@sse.com

PERMISSION GRANTED Offshore Windfarm 10.10.14 Redundant July 2020 — 2020-08-06

The Scottish Government has granted consent for Mainstream Renewable Power’s Neart na Gaoithe (NnG) offshore wind farm in the Firth of Forth. A copy of the news release issued on 10th October 2014 can be viewed by clicking Consent Press Release.

NnG is planned to start generating electricity by 2018 and, as a result, is set to be the first large-scale offshore wind farm constructed and operated in Scottish waters to be connected to the Scottish electricity system. NnG represents an investment of £1.5 billion and is expected to create hundreds of direct and indirect jobs, both during construction and throughout its operation.

The wind farm will consist of 75 turbines with the capacity to generate 450MW of electricity – enough to power 325,000 homes in a city the size of Edinburgh – which will make an important contribution to Scotland’s 2020 renewable energy target.

NEART NA GAOITHE OFFSHORE WIND FARM Redundant July 2020 — 2020-08-06

The long-term nature of the offshore wind farm project means that this page may not be updated very frequently because there may be long intervals between fresh items of news becoming available, any fresh developments that do come to our attention will be recorded in this section of the website.

Neart na Gaoithe Offshore Wind Ltd. is a subsidiary project company of Mainstream Renewable Power (UK) Ltd.  It is seeking consent to build and operate an offshore wind farm 15.5 km east of Fife Ness in the Firth of Forth, at a location known as Neart na Gaoithe (Gaelic for “might of the wind”)

The company is conducting a comprehensive consultation exercise that will continue through the whole project.  Among other aspects, this is looking at general environmental issues and the effects on wildlife.  Anyone who wishes to learn more about the project, comment on the information, or raise specific concerns is welcome to get in touch.

Contact details for the project are:

www.neartnagaoithe.com

info@neartnagaoithe.com

Zoe Crutchfield, Environmental and Consents Manager,

Mainstream Renewable Power Ltd.,

Abbey Business Centre  “The Beacon”,

176 St. Vincent Street, Glasgow, G2 5SG

The maximum generating capacity of the Neart na Gaoithe installation will be 450 MW – enough to power 325,000 homes.  Depending on the rated capacity of the turbines eventually used on the site (between 3.6 and 6MW), the estimated number of turbines is between 50 and 130.  The turbines used are likely to be a conventional 3-bladed design standing between 133 and 190m above the sea surface to the tip of the blade.

The connection point into the National Grid offered to the company is at Crystal Rig II.  The likely landing point for the cable is at Torness with the offshore cable taking the most direct subsea route from the offshore substation to the landing point.  The intention is to bury the cable from the landing point to the substation at Crystal Rig II.

It is anticipated that the application for planning consent will be submitted towards the end of 2011. If consent is granted (towards the end of 2012), the construction work will start early in 2014 and is due to be completed by late 2015, with commissioning taking place towards the end of 2015.

The project was discussed at a meeting of the Community Council on May 10 2011, following an exhibition in Innerwick Village Hall – part of the consultation process.

It is believed that if the windfarm is given the go-ahead it will provide jobs and continuing maintenance and repair work for companies in and around Dunbar.

This is likely to be a very significant development for the Dunbar area and could involve some temporary minor disruption during the construction phase.

If you have any comments, queries, or concerns about the proposal, please contact one of your local community councillors, who will do his or her best to find any additional information you need, or get in touch with the company (contact details above).

Mainstream Renewable Power Onshore Works Torness August 2016

A discrete element of advance construction works will commence in August. This involves installing concrete blocks to house cable ducts underneath the location of the new Torness cables, which are currently being installed by Scottish Power Transmission (SPT), prior to the new Torness cables being installed.

The site of the works is immediately south of the A1 junction with the Torness Power Station (Grid reference – NT 74347 74503) and its current use is for arable agriculture. However, it should be noted that SPT have already fenced off the area and stripped the site of vegetation and topsoil in preparation for their cable installation work.

The works will start of August 1st and are expected to take no longer than one month and will take place between 08.00 and 18.00 Monday to Friday and 08.00 to 13.00 Saturday. Access to the site will be from the A1 and on to the unnamed road to the south of the site which leads to Innerwick. Vehicle movements are expected to be limited to eighteen deliveries over the duration of the works in addition to approximately six cars for workforce each day.

The main onshore construction works are not expected to commence until summer 2017 at the earliest.

There will be a representative from Mainstream on site at all times, but if you have any questions about the works, please don’t hesitate to get in contact with Rosie Scurr, Environment Manager at Mainstream Renewables email rosie.scurr@mainstreamrp.com or call 0141 206 3864

Mainstream Renewable Power Thorntonloch Beach Works                              – April/May 2013

Mainstream Renewable Power will be undertaking planned survey work at Thorntonloch Beach near Innerwick from Monday 29th April until Friday 3rd May and from Monday 13th May until Friday 17th May 2013.

The work is in relation to the route of an onshore, underground electricity cable connection from the proposed 450MW Neart na Gaoithe offshore wind farm to the National Grid.

The assessments will consist of soil and rock investigations and will require small sections of the beach to be sectioned off to the public for short periods of time during the survey works. It is envisaged that these areas will be around 30 square metres at a time.

The beach will remain open throughout the survey but these cordoned off sections will be in place to allow the works to be undertaken.

A limited amount of drilling will also be undertaken to take samples from a depth of around 15 metres. All sample areas will be fully restored on completion of the works.

Mainstream Renewable Power will endeavour to keep any disruption to a minimum during this period with the large majority of the beach still being available for public access and use.

If you have any questions regarding these works please contact Ewan Walker, Environment and Consents Manager, Mainstream Renewable Power Ltd, Abbey Business Centre, ‘The Beacon’, 176 St.Vincent Street, Glasgow G2 5SG. Tel: 0141 249 6580 or email ewan.walker@mainstreamrp.com

Mainstream Renewable Power Temporary Beach Works  –  For Information

Survey work being carried out by Mainstream Renewable Power at Thorntonloch Beach due for completion today (Friday 17th May) is being extended into next week to allow final sampling work to be completed.

The assessments are in relation to the route of an onshore underground electricity cable connection from the proposed Neart na Gaoithe offshore wind farm to the National Grid.

The beach remains open to the public with small sections cordoned off to allow the works to be undertaken.

CRYSTAL RIG IV — 2020-03-02

Proposal to erect 11 further Wind Turbines at Crystal Rig

Fred Olsen Renewables, under the company name Crystal Rig IV Limited, has lodged a planning application to erect more turbines at its windfarm at Crystal Rig, Crichness, TD11 3SR, as follows:
4 further turbines with a ground to blade tip height of up to 149.9 metres,
3 further turbines with a ground to blade tip height of up to 174.5 metres,
and
4 further turbines with a ground to blade tip height of up to 200 metres.

Full details of the planning application can be found using the following link: http://www.dpea.scotland.gov.uk/CaseDetails.aspx?ID=120491 (external link — opens in a new tab)

Crystal Rig IV Postal Survey

To reflect the views of the Residents in and around Innerwick, Oldhamstocks, Spott and Stenton on the above mentioned proposal, East Lammermuir CC conducted a postal survey to ensure residents had the opportunity to make their views known through the Community Council, direct to the Scottish Government Planning & Environmental Appeals Division (DPEA).

ELCC would like to thank all residents who took time to complete and return the survey questionnaire.  176 out of 565 delivered were returned.

ELCC’s written submission to the Public Inquiry, including the survey findings can be viewed here.

The Appeal will be heard at the Public Inquiry to be held in Duns on 10 March 2020. ELCC will be represented by Chair, Chris Bruce.

 

 

 

FYI NEWSLETTER — 2016-02-27

The East Lothian Area Partnership FYI Newsletters can be accessed by selecting the links below:

From April 2017, FYI can be accessed via East Lothian Council website by clicking here  (external link — opens in a new tab) and selecting from the Available FYI downloads.

FYI 3 March 2017

FYI 17 February 2017     FYI 13 January 2017

FYI 2 December 2016     FYI 25 November 2016

FYI 18 November 2016     FYI 11 November 2016

FYI 4 November 2016     FYI 28 October 2016

FYI 14 October 2016     FYI 7 October 2016

FYI 30 September 2016     FYI 23 September 2016

FYI 16 September 2016    FYI 9 September 2016

FYI 26 August 2016     FYI19 August 2016

FYI 12 August 2016     FYI 5 August 2016

Energy Networks – Torness Underground Cable — 2016-02-16

SP Energy Networks (SPEN) is responsible for delivering a reliable, consistent and safe electricity supply to customers, often working at the request of key stakeholders and organisations. As the licensed Transmission Owner (TO) for Central and Southern Scotland they are responsible for maintaining our Transmission Network thus ensuring the reliable delivery of energy to homes and business across the country. They are shortly due to commence the replacement of a section of ageing underground cable which runs from Torness Power Station to Branxton Substation.
As part of their Stakeholder Engagement Strategy they are committed to liaising with the local community in an effort to inform them of any proposed activity which may have some form of impact. Part of this ongoing process is to provide information to the local elected members and representatives along with the wider community.
Preparatory work and mobilisation will commence 11 January 2016 with the programme of works scheduled to run through to completion in November 2016, barring any unforeseen developments. To progress the project as quickly as possible and reduce the term of impact on the community, they plan to work on a seven day basis.
There will be various stages to the project which includes the underground cable being replaced under the A1 – in order to safely complete this activity, Traffic Management Plans involving clear signage and as agreed with East Lothian Council Roads Department will be utilised. No road closure is planned to take place.
On the site compound being established as part of the early work, Prysmian Contractors intend to extend an invitation to community members to attend the site compound and be informed regarding the Project.

Iberdrola Engineering and Construction will project manage the delivery of the work and as mentioned above, Prysmian have been appointed as the principal contractor, both bringing with them a depth of experience.

SPEN would like to take the opportunity to apologize in advance for any inconvenience caused to the local community and also to ensure you that all parties involved in the work will do the utmost to keep disruption to a minimum and complete the work as quickly as possible.
They also extend thanks for support for SPEN as they undertake this work in an effort to ensure the continued delivery of a reliable, consistent and safe electricity supply.

Should you require any further information please contact Karen MacGregor or Colin Wylie by e mail or alternatively on the following phone numbers – 0141 614 3231 or 07516 461129.

A community presentation on the works will take place on Thursday 25th February 2016 in Innerwick hall at 6:30pm. Further details can be found here.

EDF extends the operating life of Torness to 2030 — 2016-02-16

EDF Energy announced on February 16th 2016 that they have extended the expected operating life of Torness and three other UK nuclear power stations – Heysham 1 and Heysham 2 in Lancashire, and Hartlepool in Teeside.

Torness and Heysham 2 have been extended by 7 years to 2030, while Heysham 1 and Hartlepool have extended by five years to 2024.

The four nuclear plants together supply electricity to around a quarter of the UK’s homes .

To read EDF Energy’s official announcement on the plants life extension please click here

LEACHATE STORAGE — 2015-03-14

image from http://viridor.co.uk image from www.viridor.co.uk

To enhance environmental sustainability, in relation to current site operations and in longer-term aftercare, Viridor is looking to invest in a local, modern Leachate (waste water) management solution sympathetic to Oxwellmains.

 

The site for the proposed Leachate Treatment Plant (LTP) is located within the boundary of the landfill site and is centred on grid reference NT 71342 75362.

The development would see leachate treated on-site using reed beds and granular filters. Comprising approximately six storage and treatment tanks the compound would be located on the southern side of the landfill, between the existing haul road and periphery screening bunds. Click here to view the location plan and here to view the proposed plan layout.

Since 1997, Viridor has managed leachate (waste water) at its Oxwellmains landfill site by storage in nearby lagoons before transporting liquid off-site by road for treatment by Scottish Water.

Viridor conducted a programme of pre-application consultation in April 2014. In addition to public notices placed in the East Lothian Courier and East Lothian News, Viridor provided a full briefing to its community liaison group, with public stakeholder events held at Halhill Sports Centre, Dunbar and Innerwick Residential Centre, Innerwick.

A planning application (15/00022/PM) was submitted to East Lothian Council in January 2015 and will be determined by the authority in due course.

PLANNED TAKEOVER — 2015-03-12

Lafarge Tarmac Quarries, cement plants and asphalt production sites, including Dunbar, are set to change hands in a £4.9billion Irish takeover.

Dublin-based CRH is buying the UK’s biggest cement maker, Lafarge Tarmac, which was formed in January 2013 following the merger of Anglo American and Lafarge’s cement, aggregates, ready-mixed concrete, asphalt and asphalt surfacing operations in the UK.

The disposal will help French building material giant Lafarge and Switzerland’s Holcim, which owns Aggregate Industries in the UK, secure regulatory clearance for their planned merger.

In order for the Lafarge Tarmac sale to CRH to proceed, the operation’s 50% owner Anglo American will first sell its stake in the business to Lafarge.

The deal will give CRH, Irelands biggest company, the number one market position in the UK in cement, aggregates, ready-mix concrete, asphalt and construction.

The process is expected to complete by the end of June 2015.

The planned takeover should not affect jobs at the Dunbar plant. A spokesman for the company said: “Lafarge Tarmac is a successful company and we do not expect any impact on jobs or investment.”

AIKENGALL IIa — 2015-03-12
Community Windpower Ltd submitted a planning application for another extension to Aikengall Wind Farm. The proposed extension is sited approximately 12.5 kilometres (km) South of Dunbar, 6 km South of Innerwick and 5 km Northeast of Cranshaws. The Aikengall IIa proposal was reduced by Community Windpower from 27 to 19 turbines following a number of objections lodged  in November 2014 including representations from East Lammermuir Community Council, East Lothian Council and Borders Council. 5 of the 19 proposed turbines will be sited in East Lothian. East Lammermuir Community Council objected on the grounds that it contravenes the East Lothian Council planning guidance on wind turbines which are too large for this location. As the turbines would be clearly visible from many points within the Oldhamstocks Conservation Village Area, the visual and landscape impact of this proposal on the conservation village is unacceptable. There would be cumulative impact – the proposed turbines above Oldhamstocks would add to the sense of being surrounded by turbines in every direction (Aikengall I, Wester Dod, Ferneylea and Hoprigshiel), and would impact on visual and landscape amenity. Residential amenity would be affected due to visual, noise and psychological impacts. ELCC also raised concerns about re-instatement of the access road and impact of construction and maintenance related traffic.

Aikengall IIa Opposed by Councils

On Wednesday 4th March 2015 Scottish Borders Councillors voted 5-2 against the Aikengall IIa proposal, despite planning officers advising against them objecting to the scheme. The Councillors said that “enough was enough and a strong message needed to be sent to Scottish Ministers that this part of the Lammermuirs was at saturation point and development should stop”. On Tuesday 10th March 2015, East Lothian Councillors followed in the footsteps of Scottish Borders Council and opposed the scheme for Aikengall IIa by a vote of 5-1. Councillor Michael Veitch said “It’s been my position for a long time that enough is enough. Aikengall and Aikengall 2 are there and several Crystal Rig phases – we are well beyond capacity.” So, the final decision on whether a further 19 turbines can be added to Aikengall wind farm in the Lammermuirs will lie with the Scottish Government, but the answer from both East Lothian and the Borders is a resounding NO!

Aikengall IIa Public Enquiry

Aikengall IIa goes to a public enquiry on 5th October 2015 in Cockburnspath Village Hall. Each party who have lodged objections to this development will be invited to attend the public enquiry, at which they will submit their reports. East Lammermuir Community Council will be represented and will focus objections on the cumulative impact which all the wind farms are having on Oldhamstocks and the residents of ELCC. Cockburnspath & Cove Community Council and Lammermuir Community Council (Scottish Borders) will also attend the enquiry, as well as both East Lothian and Borders Councils.

Aikengall IIa Planning Consent Granted 19th October 2016

Ministers have granted planning permission for Aikengall IIa despite objections from the 2 affected local authorities. Scottish Borders Council’s planning committee claimed it would “unacceptably harm” the landscape. East Lothian Council objected, claiming it was “unquestionably the wrong development in the wrong place”. East Lammermuir Community Council also opposed the scheme on the grounds that it contravenes the East Lothian Council planning guidance on wind turbines which are too large for this location. The original plans for 27 turbines were scaled down to 19 and the developers said the wind farm would “sit comfortably” within the landscape. A Scottish Government planning reporter recommended granting consent following a public local inquiry, saying the impact on the landscape was not “unacceptable” and the scheme would make a “worthwhile contribution towards the achievement of the Scottish Government’s targets for renewable energy generation”. Developers Community Windpower said the Aikengall IIa wind farm will generate £9.4 million in community benefit for areas near the development site and support the creation of about 100 jobs.

Aikengall IIa Wind Farm Turbine Deliveries Due 4th May ’21

Blade and tower component deliveries for Aikengall IIa have been confirmed and will commence on Tuesday 4th May 2021. Community Windpower expect these deliveries to last 8 weeks. Deliveries will occur during the day, with the components due to leave Grangemouth at 9:30am and expected to arrive at the A1 junction around 11:30am. They will then travel to site until 12:30pm. All abnormal loads will have a police escort. Given the distances involved, there may be flexibility in the above timings. However, all deliveries are expected to be completed outside of core travelling times. Community Windpower assures the local community that disruption will be kept to an absolute minimum. The construction work on site is almost complete and the main contractor is currently demobilising in readiness for turbine installation. Project Information
  • 19 x 145m to tip Siemens wind turbines
  • Generating capacity of 81.7MW
  • 70,000 homes powered
  • 121,000 tonnes of carbon dioxide displaced per annum
AIKENGALL WIND FARM — 2015-03-12
Aikengall Windfarm, operated by Community Windpower Ltd, is located around 3 km South of Innerwick village and 9.5 km South of Dunbar. It comprises 16 Vestas V90 wind turbines, each with a tip height of 125 metres and a generating rating of 3.0 MW. In total the wind farm has an installed capacity of 48 MW. It was commissioned in March 2009. Aikengall generates enough electricity to power around 30,000 homes. The electricity generated is fed into the local grid through the Dunbar substation and directed for local consumption.

Aikengall II Wester Dod

Wester Dod forms a consented 19 turbine southeast extension to the existing Aikengall Wind Farm, and is located approximately 11 km southeast of Dunbar and 6 km south of Innerwick. Planning was granted by Scottish Ministers in March 2013. Construction of the civil engineering works is now underway. Work on the access tracks and crane hardstandings has started, with work on the reinforced concrete foundations to support the 145m wind turbines to be completed in 2015. Paisley based Barr Construction are the main contractors and have been awarded the £7 million civils contract. Plant hire and construction personnel are to be sourced from across Scotland while as many raw materials as possible will be Scottish, including concrete and steel reinforcement for the turbine foundations. Scottish Power will complete the grid connection works for the scheme which includes maintaining the existing local infrastructure. Donna Higgins has been appointed Community Liaison Officer for the project and will be keeping in touch with local Community Councils to keep them up to date with developments and progress and to answer queries from local interest groups and individuals. To contact Donna Higgins please call 07846 077415 or email donnahiggins@redgrange.co.uk.

Indicative Construction Programme for Aikengall II:

Off-site Civil Works for Grid Connection (September 2014 – February 2015); On-site Civil Works (October 2014 – December 2015); Delivery of Concrete for Turbine Foundations (February 2015 – June 2015); Delivery of Electrical Transformer and Equipment (April 2015– June 2015); Turbine Transportation and Installation (April 2016 – June 2016) Final Grid Connection and Commissioning (July 2016). Update on Construction Programme April 2016 During construction, residents of Innerwick, Oldhamstocks and Thurston should expect disruption to the road network.

VALENCIA LANDFILL — 2015-03-09

Valencia Waste Management (formerly Viridor Waste Management)  operates the 193-acre landfill site approximately 4km south east of Dunbar. In addition to disposing of thousands of tons of solid domestic waste daily from Edinburgh and other nearby communities in a safe and environmental manner, Valencia uses two low-Btu gas generator sets to produce 3.5 MW of electricity from the methane created by decaying rubbish. All 3.5 MW is sold directly to the nearby Lafarge cement plant; and is connected by a 11kv transmission line.

As paper and other organic materials decompose in landfills, a natural by-product of that decay is methane — one of the major flammable components of natural gas. While this natural release of methane is dilute, it is a powerful greenhouse gas that can contribute to global warming. Harnessing this gas to produce electricity protects the environment while generating valuable energy.

Valencia Liaison Group Minutes (Energy Recovery Facility and Landfill Restoration)

January 2024

Report on August 2023 Fire Incident (obtained through an FOI request)

https://eastlammermuircommunitycouncil.org.uk/viridor-incinerator/

https://eastlammermuircommunitycouncil.org.uk/polymer-recycling-facility/

SEPA PERMIT — 2015-03-09

In February 2015, Lafarge Tarmac cement plant was awarded a new Part A Environmental Permit by the Scottish Environment Protection Agency (SEPA).

The permit is issued and monitored by SEPA to meet EU standards of operation for industrial sectors, and sets out conditions the cement plant must meet in order to function, including maximum levels of emissions which can be released while operating.

Florin Stoiean, plant manager at Lafarge Tarmac Dunbar, commented “Obviously, this is an essential piece of legislation and we always aim to not only meet the mandatory standards but exceed these where we can, while also looking ahead at evolving regulations which address future requirements.”

WHITESANDS QUARRY — 2015-03-09

Barnacle goose Barnacle goose

Lafarge Tarmac entered into an agreement with RSPB Scotland regarding the development of Whitesands quarry as a nature and leisure facility in 2013. It has since become home to some important winter visitors from Northern climes, Eastern Europe and Russia including pochard duck and barnacle geese.

The site is quickly becoming a haven for rarer species because of its unique freshwater habitat so close to the coast.

In late October and early November 2014 four species of geese were using the lake. These included pink footed geese from Iceland and also barnacle geese from the Svalbard Islands between Norway and the North Pole.

It is believed that with the right combination of habitat creation and public access management Whitesands Quarry has the potential to attract regionally important populations of waders and wildfowl.

TARMAC (A CRH Company) — 2015-03-09
Tarmac (formerly Lafarge Tarmac)  is Scotland’s only cement manufacturing operation. The Dunbar plant is one of East Lothian’s most enduring businesses and has helped build the equivalent of 6.5 million houses since it started operations under Associated Portland Cement Manufacturers (and then Blue Circle Industries PLC) in 1963. The site at Oxwell Mains was chosen because it had the ideal proportions of shale and limestone for the production of cement. The site has benefited from some £100m of investment since it was built, including a highly efficient kiln and preheater tower and the £20m gas scrubber built in 2007, which has halved sulphur and dust emissions. The Dunbar plant has made significant inroads into reducing its greenhouse gas emissions in recent years by sourcing 20 per cent of its power requirements from the methane produced by the neighbouring Viridor landfill site, maximising use of its own raw materials, shifting significant numbers of vehicle movements from road to rail and utilising increased levels of waste-derived fuels that leave no by-product.

Links with the Local Community

Tarmac Local Community Liaison Group reports that the company remains committed to open communications and lasting relationships with the local community, ensuring ongoing engagement and transparency within the Dunbar plants operations. Tarmac encourage comments/feedback on any issue or concerns the public may have. Any comments/complaints/concerns regarding,for example, smells or environmental issues, should be forwarded to Environmental Coordinator Gale Coates on 01368 861363 or email gale.coates@lafargetarmac.com. These will be investigated as quickly as possible.
TORNESS POWER STATION — 2015-03-05
Torness is sited approx' 6 miles south of Dunbar. It is operated by EDF Energy and is capable of supplying electricity to over 2 million UK homes. Station Director: Robert Gunn Reactor type: 2 Advanced Gas-cooled Reactors Total supply to the national grid: 1190 MW Coolant: Carbon dioxide gas (CO2) Start of construction: 1980 Start of generation: 1988 Estimated end of generation: 2030 Employees: ~550 full time EDF plus over 180 full time contractors

Local Liaison Council Meetings

EDF Energy hold annual Local Liaison Council (LLC) Meetings with local people, the media, council and emergency services representatives and local politicians to maintain regular communications about the nuclear site. LLC Minutes of Meeting 19 March 2015 LLC Minutes of Meeting 7 April 2016 LLC Minutes of Meeting 25th June 2020     via Zoom The next LLC is 24 March 2021, 10am-12pm  via Zoom For more information, contact Ashleigh Dickson, EDF Energy, on 01368 873847 or  email ashleigh.dickson@edf-energy.com Torness Community Reports can be accessed below: January 2015 (external link — opens in a new tab)      February 2015      May 2015     October 2015 November 2015 January 2016     October 2016 October 2017 January 2018       First Quarter Visitor Centre Free Activities 2018 May 2018    
VIRIDOR CREDITS FUNDING — 2015-03-04

Viridor Credits Environmental Company is an independent, not-for-profit organisation which provides funding for community, heritage and biodiversity projects around the UK through the Landfill Communities Fund.

Viridor Credits is a company limited by guarantee (No. 4293742) and is a Distributive Environmental Body (DEB) registered with ENTRUST, the regulator of the Landfill Communities Fund (Reg No. 331293). It is also registered as a charity (No. 1096538).

Viridor Credits was set up to administer the LCF on behalf of Viridor. It is, however, a wholly independent company, separate from Viridor’s operations.

Viridor Credits is based in Taunton, Somerset.

Viridor Credits provides funding for a huge range of projects and will consider eligible applications on their merits and in light of the funding available. In general, a project needs to be located within 10 miles of a Viridor Landfill Site. Applications for projects located within 10 miles of a Viridor Landill Site can fall under the provision of one of the categories listed below.

1. Community – Provision or maintenance of public amenities;

2. Conservation – Promotion of biological diversity through:

the provision, conservation, restoration or enhancement of a natural habitat

or

the maintenance or recovery of a species or its habitat on land or water

3. Heritage – Maintenance, restoration or renovation of structures of historical or architectural importance or those used for religious worship, provided they offer public access.

Viridor Credits have been funding projects in the Dunbar area for over 10 years, considering applications for funding via a Steering Group made up of local volunteers from community groups, councillors and community-minded individuals in order to best direct this funding for maximum benefit to the community.

For more information on Viridor Credits and the Funding Application Process goto their website by clicking here (external link — opens in a new tab)

VIRIDOR INCINERATOR — 2015-03-04

An Artist's Impression of Viridor Facility An Artist’s Impression of Valencia Facility

Energy Recovery Facility (ERF) near Dunbar.

The facility, located at its rail linked Oxwellmains waste treatment hub, secured planning consent for the site from Scottish Ministers in December 2010, and approval from SEPA in 2011.

 

In 2012, Viridor (now Valencia) got the go-ahead from East Lothian Council to vary planning conditions to allow waste to be transported to the new incinerator facility from anywhere in Scotland – a move that provoked anger from local protesters.

The plant uses a combination of moving grate combustion technology, anaerobic digestion and recycling technologies. In-line with the Scottish Governments ambitions to deliver a zero waste circular economy, the site will generate 30 MW of energy from waste which it will supply direct to the grid – enough to power 39,000 homes, as well as up to 10 MW of heat which will be available for local use.

Babcock & Wilcox Vølund (BWV) and its construction partner, Interserve were  selected by Viridor to design and build the planned waste to energy power plant .

B&W Vølund’s scope accounts for more than two-thirds of the contract value and includes two WTE boilers, the DynaGrate® dynamic fuel combustion system, steam turbine and a dry flue gas cleaning system. The consortium also will test and commission the plant.

The Dunbar plant will be able to process up to 300,000 tonnes per annum and will be part of many measures to help the Scottish government meet an ambitious target of landfilling zero biodegradable municipal waste by 2021.

The plant was scheduled to go online in the fourth quarter of 2017.

The plant will only accept post-recyclable material – material that can’t be recycled – and will operate to the highest national and international standards, stringently regulated by the Scottish Environment Protection Agency.

At least 350 skilled and semi-skilled workers were employed throughout the three year construction phase, including a range of professional, skilled, entry-level roles and apprenticeships. The project also aims to deliver a range of community benefits focused on employment and training, providing support for local business and education through Viridor’s partnership with the Engineering Development Trust.

On completion the new Energy Recovery Facility will support 55 full-time jobs, supporting the East Lothian economy by an estimated £10 million per year.

BENEFIT FUND AWARDS — 2015-01-26

Beneficiaries of the awards, recommended by both Fred Olsen Renewables Ltd and ELCC as the Directors of the Crystal Rig III Community Benefit Fund, include:

November 2023 : Circa £60K awarded

Innerwick:  Horticultural Society and Parent Council
Oldhamstocks:  Country Dance and SWI
Spott: Community Association, Spott & Belhaven Church
Stenton:  None
Others: Scottish Flag Centre, Scottish Sheepdog trials, The Space, Irish Dance School

May 2023 : Circa £265K awarded

Innerwick: IPWA – Village Hall Project (£170k funding reserved for future building works)
Oldhamstocks:  Horticultural Society and SWI
Spott: SWI
Stenton:  Horticultural Society, Community Association, Footlights, Bowling Club
Others: Dunbar Colts Football Club, Realise Scotland, Black Agnes Festival, Irish Dance.

November 2022 : Circa £58K awarded

Innerwick:  Parent Council and Insulate Innerwick
Oldhamstocks: SWI
Spott: Community Association, Menopause & Me
Stenton:  Primary School and Bowling Club
Others: Thorntonloch Caravan Site

May 2022 : Circa £64K awarded

Innerwick:  Horticultural Society and Primary School
Oldhamstocks:  Horticultural Society and SWI
Spott: Community Association 
Stenton:  Horticultural Society
Others: The Ridge, Dunbar Walking Football Club

November 2021 : Circa £102K awarded

Innerwick: Parish Welfare, Horticultural Society, Primary School, Parent Council
Spott: Community Association, SWI
Stenton: Community Association
Others: The Ridge

May 2021 : Circa £18K awarded

  • Innerwick: Horticultural Society, Parish Welfare, Ladies who lunch
  • Spott: Community Association
  • Stenton: Community Association, Horticultural Society, The Footlights, Primary School
  • Others: Enjoy Leisure

November 2020: Circa £26K awarded

  • Innerwick: Horticultural Society, Primary School
  • Spott: Community Association, Country Dancing, SWI, Spott Church
  • Stenton: Bowling Club
  • Others: Parish of Dunglass, The Ridge

May 2020: Applications suspended due to Coronavirus

December 2019: Circa £25K awarded

  • Innerwick: Horticultural Society, Aine Hay Academy of Irish Dance
  • Oldhamstocks: Playpark, WRI
  • Spott: Community Association
  • Stenton: Community Association, Bowling Club, Primary School
  • Others: Parish of Dunglass

May 2019: Circa £20K awarded

  • Innerwick: Horticultural Society
  • Oldhamstocks: Community Association, Horticultural Society, Country Dance Group, WRI, Play-park
  • Spott: Community Association, Country Dancing, WI
  • Others: Parish of Dunglass, Dunbar Singalong for People with Dementia

November 2018: Circa £23K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Aine Hay Academy of Irish Dance, Lunch Club
  • Oldhamstocks: WRI, Horticultural Society
  • Spott: Community Association, Spott Church
  • Stenton: Community Association, Stenton Church
  • Others: ELCC Skateraw WW1 Memorial

May 2018: Circa £28K awarded

  • Innerwick: Horticultural Society, Primary School
  • Oldhamstocks: WRI, Horticultural Society
  • Spott: Community Association, SWI
  • Stenton: Community Association, Bowling Club
  • Others: Dunbar Choral Society

November 2017: Circa £10K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Aine Hay Academy of Irish Dance, School Parent Council
  • Oldhamstocks: WRI, Horticultural Society
  • Spott: Community Association, WRI
  • Stenton: Stenton Church
  • Others: Dunbar Basics Food Bank

May 2017: Circa £13K awarded

  • Innerwick: Horticultural Society, Primary School
  • Oldhamstocks: WRI, Horticultural Society
  • Spott: Community Association, WRI
  • Stenton: Bowling Club, Stenton Church
  • Others: Parish of Dunglass

December 2016: Circa £62K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Primary School
  • Oldhamstocks: Community Association, WRI, Horticultural Society, Keep Fit
  • Spott: Community Association
  • Stenton: Stenton Church
  • Others: Scottish Air Ambulance Service

November 2015: Circa £200K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Primary School, Innerwick Church, Toddlers Group
  • Oldhamstocks: WRI, Horticultural Society, Keep Fit
  • Spott: Community Association, WRI, Spott Church
  • Stenton: Community Association, Bowling Club, Stenton Church, Primary School

May 2015: Circa £82K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Primary School, Play-park
  • Oldhamstocks: Horticultural Society, Keep Fit
  • Spott: Community Association, WRI
  • Stenton: Community Association
  • Others: Dunbar & District Twinning Association. Scottish Air Ambulance Service

November 2014: Circa £87K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Primary School, Toddler Group
  • Oldhamstocks: Community Association, WRI, Horticultural Society, Country Dancing, Keep Fit
  • Spott: Community Association, WRI, Country Dancing, Spott Church
  • Stenton: Community Association, Bowling Club, Stenton Church, The Bughts
  • Others: Parish of Dunglass

May 2014: Circa £36K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Primary School, Ladies Group
  • Oldhamstocks: Community Association, WRI, Horticultural Society, Keep Fit
  • Spott: Community Association, WRI, Spott Church, Country Dancing
  • Stenton: Bowling Club, Stenton Church, The Bughts
  • Others: Parish of Dunglass, The Scottish Air Ambulance Service

November 2013: Circa £43K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Primary School, Toddler Group, Brownies, Ladies who Lunch
  • Oldhamstocks: Community Association
  • Spott: Community Association, WRI, Country Dancing, Spott Church
  • Stenton: Community Association, Cricket Club
  • Others: Parish of Dunglass

April 2013: Circa £20K awarded

  • Innerwick: Parish Welfare, Horticultural Society, Community Cafe, Primary School, Playgroup, Brownies
  • Oldhamstocks: Community Association, WRI, Horticultural Society, Keep Fit
  • Spott: Community Association, Country Dancing, Spott Church
  • Stenton: Community Association, Cricket Club, Stenton Church
  • Others: Parish of Dunglass, Dunbar Rugby Club U15’s tour

January 2013: Circa £6K awarded

  • Oldhamstocks: Community First Responders
  • Spott: WRI
  • Stenton: Bowling Club, Stenton Singers

Year 2012: Circa £17K awarded

  • Innerwick: Horticultural Society, Playgroup, Brownie Group, Rainbow Club
  • Oldhamstocks: Community Association, WRI, Horticultural Society, Keep Fit
  • Spott: WRI, Country Dancing, Spott Church
  • Stenton: Bowling Club, Parish of Traprain
  • Others: Parish of Dunglass, The Ridge, North Lights
GRAZING AT BARNS NESS — 2015-01-16

The annual Sheep grazing in a fenced off area west and south of the lighthouse are part of an ELC initiative to improve the botanical biodiversity of the area.

 

Blackcastle Turbine — 2015-01-16

No additional text was published with this record.

BLACKCASTLE COMMUNITY TURBINE — 2015-01-16
Proposal to Erect a 500kW Wind Turbine on Blackcastle Hill Dunbar Community Energy Company lodged a planning application for a 500kW wind turbine on Blackcastle Hill on November 2nd 2012.  The 56m high turbine would be wholly community owned with all profits being disbursed through a community investment fund for the Dunbar and East Linton Ward.  It is estimated that around £4 million pounds will be available for local projects over the 20 year life of the turbine. Dunbar Community Energy Company is a trading subsidiary of the charity Sustaining Dunbar and is run by a board of volunteers.  They have developed a proposed procedure for disbursing the profits by means of a ‘Project Evaluation Group’ Further information is available on the website: www.dunbarcommunityenergy.org.uk (external link — opens in a new tab) Full details of the planning application can be found at www.eastlothian.gov.uk (external link — opens in a new tab) planning ref no. 12/00874/P, and an exhibition will be placed in Innerwick Village Hall for a two week period from 4th to 18th February 2013 so that the community have a chance to have a look at the proposal in detail. East Lammermuir Community Council encourages residents to look closely at this proposal.  The location of the turbine will have most impact on those in the Innerwick area. If you have any views on the Blackcastle Hill proposal, we would be grateful if you would advise us (confidentially) by Monday 18th February 2013 by emailing us at ELCC.Comms@gmail.com   Blackcastle Hill Wind Turbine Proposal Survey  East Lammermuir Community Councillors undertook a postal questionnaire which was delivered to 350 homes in the Spott/Innerwick/Oldhamstocks area, seeking their views on the above planning application.  To view the questionnaire, click on the ‘Blackcastle Hill Wind Turbine Proposal survey’ link below. A total of 115 questionnaires were returned, a 33% response rate and the number of adults responding was 215.

Blackcastle Hill Wind Turbine Proposal survey (original linked PDF no longer available)

Opinion Number of individual responses Percentage
Strongly oppose

104

48

Tend to oppose

14

7

Neither support nor oppose

28

13

Tend to support

30

14

Strongly support

39

18

Total

215

100

  ELCC agreed to adopt the position painted in these figures – that is, a clear majority of respondents oppose this planning application and would therefore write to ELC Planning Department with their note of objection highlighting the visual, landscape, noise impact and the application being outwith the ELC planning guidelines, by 28 February, 2013. To view the objection letter forwarded to ELC Planning click on the link below:

ELCC Blackcastle Hill objection (original linked PDF no longer available)

Blackcastle Update May 2013 East Lothian Council Officers have recommended that the application for the turbine on Blackcastle Hill be refused. However, the decision has been called in and will now be considered by the Planning Committee at the Town House in Haddington on Tuesday 7th May 2013. ELCC will be making a further statement of objection at this meeting. Blackcastle Update 7th May 2013 The Planning Committee upheld East Lothian Council Officers recommendation and unanimously rejected the application for the Turbine at Blackcastle Hill. Blackcastle Update 30th August 2013 Dunbar Community Energy Company have lodged an appeal to the Scottish Government to overturn the decision made by ELC on 7th May. East Lammermuir Community Council submitted a letter to the Directorate for Planning and Environmental Appeals reiterating it’s strong objection and asking that the appeal be dismissed. Blackcastle Update 4th November 2013 The appeal made by Dunbar Community Energy Company to the Scottish Government has been dismissed by the Reporter and the planning permission REFUSED. The Reporter’s decision is final, but Dunbar Community Energy Company will have the right to appeal to the Court of Session. However, an appeal to the Court of Session can only be made on a point of law.
EAST LAMMERMUIR CHRONICLE — 2015-01-15
Planning and Consenting — 2015-01-14

Offshore Consents – Original Application

In 2009, three years of offshore environmental surveys commenced to gather information on habitats and species, physical conditions and human activities at the NnG site. This information was collected to inform a detailed Environmental Impact Assessment (EIA), which was submitted with an application for consent for the offshore elements. This information is set out in an Environmental Statement, which can be viewed on the ‘downloads’ section of this website. The application for consent for the offshore elements of the project was submitted to Scottish Government Ministers (Marine Scotland) in July 2012. Consent was granted in October 2014.

Judicial Review

In January 2015 a Judicial Review of the Scottish Ministers’ consenting process was raised by the RSPB which delayed NnG along with three other offshore wind farm projects. The RSPB’s concerns were initially upheld in a decision of the Outer House of the Court of Session in July 2016. This was appealed by Scottish Government Ministers and in May 2017 the Inner House overturned the original decision, resulting in the reinstatement of the consents. In June 2017, the RSPB sought leave to appeal to the Supreme Court which was denied by the Inner House. In August 2017, the RSPB sought leave to appeal to the Supreme Court in London directly which was subsequently refused in November 2017. The Supreme Court’s decision to refuse RSPB Scotland’s application to appeal the Scottish Court’s earlier ruling clears the way to proceed with the construction of NnG. Read the full press statement here.

Onshore Planning Permission

An application for the onshore grid connection infrastructure was submitted to East Lothian Council in November 2012. This includes 12.3 km of buried cable and a new substation. Planning permission was granted in June 2013.  
NEART NA GAOITHE OFFSHORE WIND FARM — 2015-01-14

The Neart na Gaoithe (NnG) offshore wind farm will be located 15.5 km off the Fife coast and covers an area of approximately 105 km2. EDF Renewables UK acquired the project in May 2018 as part of a competitive bidding process.

The project has the potential to generate 450MW of renewable energy, which is enough power to supply around 375,000 Scottish homes – more than the whole of Edinburgh and will offset over 400,000 tonnes of CO2 emissions each year. The NnG site was chosen because it combines technical, economic and environmental deliverability. Some of the criteria that formed part of the site selection process included; water depth, ground condition, expected energy yield, access to port facilities and more. NnG is one of two Scottish offshore wind farms to have won a Contract for Difference (CfD). It gives the wind farm an inflation-linked strike price for the electricity it produces for a period of 15 years. This revenue stream makes the project financeable and will enable it to reach financial close. A map of the proposed project is shown below:

Project facts

  • Neart na Gaoithe means ‘Strength of the Wind’.
  • Comprises 54 x Siemens SWT-6.0-154 turbines with a rotor diameter of 154m.
  • The project has the potential to generate 450MW of renewable energy.
  • When fully operational, it will generate enough electricity to power over 375,000 households.
  • NnG represents an investment of £2 billion in Scotland’s energy infrastructure.
  • It will offset over 400,000 tonnes of CO2 emissions each year.
  • Onshore grid connection is at Crystal Rig onshore wind farm near Dunbar, East Lothian.
  • Distance of approximately 1 km between each turbine.
  • The closest turbine will be a minimum of 15.5 km from the shore.
  • The NnG site will be approximately 105 km2.
  • It is expected to be commissioned in 2023