Energy Projects Traffic and Travel drop-in — report from 20 October 2026
A Community Traffic and Travel Forum drop-in event took place on Tuesday 20th October in Innerwick Outdoor Centre.. Project information from the event is now available to view online.
-
Traffic & Travel drop-in — 20 October 2026
Drop in at Innerwick Old School / Outdoor Centre, 3–7pm on 20 October 2026, for updates and questions about energy-project construction traffic and travel.
-
Hedgerows: Branxton and Crystal Rig IV update, September 2026
This update records information published on 18 September 2026 about hedgerows and tree planting near energy-project works. Branxton substation and the C121 near Innerwick SP Energy Networks said it was reviewing detailed plans for road widening at the entrance to the new Branxton substation. Further surveys and assessment of clearance requirements were needed before decisions…
-

Innerwick U215/C121 closures — August–September 2026 updates
SP Energy Networks’ August 2026 update on road closures near Innerwick and access restrictions at the Bilsdean slip road. Check the operator’s latest information before travelling.
-

Vehicle signage
The Community Traffic and Travel Forum’s proposal for energy projects for construction vehicle signage has now been adopted for all SP Energy Networks projects. We hope this will make it easier for community members to identify which project construction vehicles are associated with, and make reporting of any issues more streamlined. Thank you to SPEN…
-

Branxton enabling works — June–October 2026 traffic programme
Historical works programme: This June 2026 announcement described works scheduled through October 2026. Some arrangements were subsequently revised. Check the latest project notices; this page does not confirm current road status. To complete the new A1 slip road the temporary traffic barrier must be removed to tie in the new road. This requires night shift…
-
Branxton substation — February 2026 path and traffic programme
Historical works notice: This programme relates to February 2026. Check current project and roadworks information before travelling; this post does not confirm completion. Bypass path and Bilsdean temporary traffic lights Branxton Project will be starting the bypass path in the opposite field South of the C120 on the 2nd February with one weeks work planned…
-

Branxton enabling works — January 2026 traffic notice
Historical traffic notice: The temporary traffic lights described below were scheduled for 20–22 and 27–29 January 2026. This is not a current road-status report. Enabling works to construct a slip road off the A1 and other road works are due to begin shortly. To support this work, traffic management will be in place in the…
-

Beth’s Blog – a partnership approach to construction impacts
What a whirl these last few months have been! Since I last wrote a blog post I have been developing and taking forward a set of five key priorities (external link — opens in a new tab) for the Energy Projects Partnership, with a significant focus on a series of workshops exploring ways to deliver…
-
Lorries in Our Lanes — 10 November 2025 meeting and report
Past event: This meeting took place on 10 November 2025. The invitation is retained below, followed by the meeting summary and presentations. Monday 10th November 6:30 – 8pm Innerwick Old School House Join us on Monday 10th November for updates on the current and upcoming construction of energy projects, focused on their impacts on traffic…
-

Planning consent granted for Branxton Substation
East Lothian Council Planning Committee unanimously voted to grant consent for this keystone development at their meeting held 5 November. 27 residents submitted a total of 61 objections to the scheme. Two local residents and the Community Council spoke in objection at the committee but did not win the day. The notice of planning consent…