- Barns Ness Terrace will be closed from 2nd-13th July. This is to allow for surfacing works.
- The road must remain closed for the duration of the works to protect the public from a live construction site featuring heavy machinery and vehicle movements.
- The closure has been approved by East Lothian Council, and a map of the diversion is included in the link below
- Clear signage will be installed a week before the closure at prominent positions at each end of the length of the road closure notifying users of the closure. Signage will be inspected regularly throughout the closure period and replaced if necessary.
- The road will be closed off to the public using steel Heras fencing. The fencing will be inspected regularly to ensure it remains secure throughout the closure period.
DUNGLASS – BILSDEAN COMPOUND PORTACABIN DELIVERIES
Other EGL1 information from Prysmian. A quantity of portacabins will be delivered to the Bilsdean compound via the road going past Dunglass from w/c 29th June:
Deliveries via Dunglass traffic route w/c 29 June
- Approximately 25 vehicle movements are scheduled between Monday 29 June-Friday 3 July, between the hours of 7am-7pm.
- The vehicles will be delivering standard size portacabins and will use the Dunglass traffic route. If the Branxton slip road is open by these dates, the vehicles will use this route.
- The vehicle movements will occur across the week.
- No traffic management or diversions will be required. The vehicle movements will not cause traffic disruption.